- Project Number:
- SAP 066-598-025
- Contract Number:
- 2570
- Other Project Numbers:
- Project Description:
- Wall Street Road Bridge Improvements - CR 79 (New Bridge No. 66J92)
-Box Culvert
- Construction Location:
- CR 79 (Wall Street Road)
- City or Township:
- Bid Opening:
- 12/03/2024 10:00 AM
- Expected Award Date:
- 12/17/2024
- Project Start Date:
- 01/01/2025
- Construction Start Date:
- 01/01/2025
- Construction End Date:
- 06/15/2025
- Work Type:
- Pipe and Culvert
- Project Type:
- Bridges
- Highest Funding Level:
- State
- DBE Project:
- No
Wall Street Road Bridge Improvements - CR 79 (New Bridge No. 66J92)
-Box Culvert
Project Major Items:
Number | Item | Units | Quantity |
---|
2101.505/00020 | CLEARING | ACRE | 0.42 |
2101.505/00030 | GRUBBING | ACRE | 0.42 |
2106.507/00080 | SELECT GRANULAR EMBANKMENT (CV) | C Y | 2,970.00 |
2106.507/00130 | COMMON EMBANKMENT (CV) | C Y | 1,346.00 |
2401.601/00010 | STRUCTURE EXCAVATION | LS | 1.00 |
2412.502 | 12X8 PRECAST CONCRETE BOX CULVERT END SECTION | EACH | 4.00 |
2412.503/12080 | 12X8 PRECAST CONCRETE BOX CULVERT | L F | 200.00 |
2442.501/00010 | REMOVE EXISTING BRIDGE | LS | 1.00 |
2451.507/00250 | FINE AGGREGATE BEDDING (CV) | C Y | 325.00 |
2511.602/0010100 | CROSS VANE BOULDER | EACH | 70.00 |
2573.601 | TEMPORARY STREAM DIVERSION SYSTEM | LS | 1.00 |