- Project Number:
- CP 0000-475845
- Contract Number:
- CP 0000-475845
- Other Project Numbers:
- CP 0000-475845: SAP 069-030-049
- Project Description:
- CP 0000-475845, SAP 069-030-049; SAP 016-612-082; SAP 038-030-012
- Construction Location:
- Various County State Aid Highways in Cook County, Lake County, and St. Louis County
- City or Township:
- Bid Opening:
- 04/11/2024 10:00 AM
- Expected Award Date:
- 05/07/2024
- Project Start Date:
- 06/03/2024
- Construction Start Date:
- 06/03/2024
- Construction End Date:
- 08/02/2024
- Work Type:
- Traffic Marking/Striping
- Project Type:
- Road and Street
- Highest Funding Level:
- State
- DBE Project:
- No
Pavement marking project located on various County State Aid Highways in Cook County, Lake County and St. Louis County.
Project Major Items:
Number | Item | Units | Quantity |
---|
2582.503/10106 | 6" SOLID LINE PAINT | LIN FT | 469,357.00 |
2582.503/20106 | 6" SOLID LINE PAINT GROUND IN (WR) | LIN FT | 304,509.00 |
2582.503/40104 | 4" SOLID LINE MULTI-COMPONENT GROUND IN (WR) | LIN FT | 122,044.00 |
2582.503/40106 | 6" SOLID LINE MULTI-COMPONENT GROUND IN (WR) | LIN FT | 342,375.00 |
2582.518/03040 | PAVEMENT MESSAGE PREFORM TAPE GROUND IN | SQ FT | 5,114.00 |