Project Number:
S.P. 8611-30 & S.P. 086-596-004
Contract Number:
Other Project Numbers:
0W1.123025, S.P. 8611-30, S.P. 086-596-004, HIP-CDS 8623 (220), Agreement No. 1046929
Project Description:
TH 24/Hemlock St Roundabout with Sidewalk and Pedestrian Improvement, Xcel Energy Lighting, Full Depth Reclamation on Hemlock St
Construction Location:
TH 24 & Hemlock St
City or Township:
Annandale
Bid Opening:
06/13/2023 3:30 PM
Expected Award Date:
06/26/2023
Project Start Date:
06/28/2023
Construction Start Date:
07/05/2023
Construction End Date:
10/27/2023
Work Type:
Reconstruct
Project Type:
Road and Street
Highest Funding Level:
Federal
DBE Project:
Yes
TH 24/Hemlock St Roundabout with Sidewalk and Pedestrian Improvement, Xcel Energy Lighting, Full Depth Reclamation on Hemlock St
Project Major Items:
NumberItemUnitsQuantity
1REMOVE BITUMINOUS PAVEMENTSQ YD9,722.00
10DRILL & GROUT REINFORMCEMENT BAR (EPOSXY COATED)EACH20.00
11TYPE SP 12.5 WEARING COURSE MIXTURE (3,B)TON4,931.00
12TYPE SP 12.5 NON WEARING COURSE MIXTURE (3,F)TON5,820.00
13REINFORCEMENT BARSPOUND560.00
1415" RC PIPE SEWER DESIGN 3006 CLASS IIILIN FT1,208.00
154" PERF PE PIPE DRAINLIN FT2,621.00
1624" RC PIPE SEWER DESIGN 3006 CLASS IIILIN FT326.00
17CONST DRAINAGE STRUCTURE DES 48-4020LIN FT66.00
186" CONCRETE WALKSQ FT12,209.00
196" CONCRETE WALK SPECIALSQ FT1,841.00
2REMOVE WATER MAINLIN FT150.00
20CONCRETE CURB & GUTTER DESIGN B612 (MODIFIED)LIN FT1,463.00
21CONCRETE CURB & GUTTER DESGIN S512 (MODIFIED)LIN FT1,467.00
22CONCRETE CURB & GUTTER DESIGN S524LIN FT1,104.00
23TRUNCATED DOMESSQ FT343.00
24SIGNSQ FT429.00
25TRAFFIC CONTROLLUMP SUM1.00
26DECIDUOUS SHRUB NO 5 CONTSHRUB109.00
27SEEDINGACRE1.00
28HYDRAULIC REINFORCED FIBER MATRIX POUND2,333.00
29MULCH MATERIAL TYPE 6SQ YD58.00
3EXCAVATION - COMMON (P)CU YD8,581.00
304" SOLID LINE MULTI-COMPONENT GROUND IN (WR)LIN FT17,590.00
4SELECT GRAN EMBANKMENT (CV) (P)CU YD4,402.00
5COMMON ENBANKMENTCU YD1,193.00
6AGGREGATE SURFACING (CV) CLASS 1CU YD225.00
7AGGREGATE BASE (CV) CLASS 6 (P)CU YD1,687.00
8FULL DEPT RECLAMATIONSQ YD31,103.00
9MILL BITUMINOUS SURFACE (2.0")SQ YD3,000.00
Project Owner:

City of Annandale
Kelly Hinnenkamp, City Admin
30 Cedar St E
Annandale, MN   55302
(320) 274-3055
(320) 274-5728
khinnenkamp@annandale.mn.us
Project Engineer:

Bolton & Menk
Derek Arens
12224 Nicollet Ave
Burnsville, MN   55337
(612) 655-1546
(952) 890-8065
derek.arens@bolton-menk.com