- Project Number:
- 23-05
- Contract Number:
- 23-05
- Other Project Numbers:
- SAP Nos. 160-020-050, 160-020-049, 062-651-073, 062-646-041
- Project Description:
- 2023 Pathway Project - Excavation, grading, bituminous milling, bituminous surfacing, concrete sidewalk, retaining wall construction, curb and gutter, watermain, restoration and landscaping.
- Construction Location:
- Project includes multiple locations in Roseville in Ramsey County, Minnesota. Lexington Avenue, Cleveland Avenue and Marion Steet.
- City or Township:
- Roseville
- Bid Opening:
- 05/30/2023 2:30 AM
- Expected Award Date:
- 06/05/2023
- Project Start Date:
- 06/19/2023
- Construction Start Date:
- 06/19/2023
- Construction End Date:
- 10/18/2023
- Work Type:
- Trail Construction
- Project Type:
- Sewer and Water
- Highest Funding Level:
- Federal
- DBE Project:
- No
2023 Pathway Project - Excavation, grading, bituminous milling, bituminous surfacing, concrete sidewalk, retaining wall construction, curb and gutter, watermain, restoration and landscaping. Project includes multiple locations in Roseville in Ramsey County, Minnesota.
Project Major Items:
Number | Item | Units | Quantity |
---|
2105.507 | COMMON EXCAVATION (EV) | C Y | 790.00 |
2232.504/00040 | MILL BITUMINOUS SURFACE (1.5") | S Y | 3,080.00 |
2360.509/13250 | TYPE SP 9.5 NON WEARING COURSE MIXTURE (3,B) | TON | 300.00 |
2411.618/00005 | MODULAR BLOCK RETAINING WALL | S F | 820.00 |
2411.618/00007 | PREFABRICATED MODULAR BLOCK WALL | S F | 600.00 |
2504.603 | 6" WATERMAIN DUCTILE IRON CL 52" | L F | 56.00 |
2521.518/00040 | 4" CONCRETE WALK | S F | 9,135.00 |
2531.503/02315 | CONCRETE CURB & GUTTER DESIGN B618 | L F | 450.00 |
2574.604\00001 | TURF ESTABLISHMENT WITH HYDROSEED | S Y | 7,400.00 |
2582.518/06000 | CROSSWALK MULTI-COMPONENT | S F | 216.00 |