- Project Number:
- SP 071-070-046
- Contract Number:
- 22009
- Other Project Numbers:
- Project Description:
- 2023 HSIP 6" Edgeline Striping
- Construction Location:
- Sherburne County
- City or Township:
- Bid Opening:
- 06/06/2023 1:00 PM
- Expected Award Date:
- 06/20/2023
- Project Start Date:
- 07/10/2023
- Construction Start Date:
- 07/10/2023
- Construction End Date:
- 08/25/2023
- Work Type:
- Traffic Marking/Striping
- Project Type:
- Road and Street
- Highest Funding Level:
- Federal
- DBE Project:
- No
Edgeline Striping on various county roads (54.2 miles)
Project Major Items:
Number | Item | Units | Quantity |
---|
2582.503/36106 | 6" SOLID LINE MULTI-COMPONENT GROUND IN | L F | 560,750.00 |