Project Number:
SP 040-618-009
Contract Number:
Other Project Numbers:
MINN. PROJ. NO. STBG 4023 (030)
Project Description:
Mill, Stabilized Full Depth Reclamation, and Overlay
Construction Location:
On CSAH 18, between CSAH 21 and CSAH 15
City or Township:
Kasota and Cleveland TWPs
Bid Opening:
04/05/2023 1:00 PM
Expected Award Date:
04/18/2023
Project Start Date:
07/10/2023
Construction Start Date:
07/10/2023
Construction End Date:
09/29/2023
Work Type:
Mill and Overlay
Project Type:
Road and Street
Highest Funding Level:
Federal
DBE Project:
Yes
NOTICE

NOTICE TO CONTRACTORS - Sealed bids will be received until 1:00 p.m., Wednesday, April 5th, 2023 by Danielle Ongie, County Auditor of Le Sueur County, 88 South Park Avenue, Le Center, Minnesota on behalf of the County Board of Commissioners for the Mill, Stabilized Full Depth Reclamation, Bituminous Overlay Project on CSAH 18: SP 040-618-009, MINN. PROJ. NO. STBG 4023 (030). Total Project Length of 6.195 miles.

Minimum wage rates to be paid by the Contractors have been predetermined and are subject to the Work Hours Act of 1962, P.L. 87-581 and implementing regulations.

A minimum goal of 10.5 % Good Faith Effort to be subcontracted to Disadvantaged Business Enterprises.

The approximate major quantities are as follows:
Class 1 Aggregate Shouldering 12,000 Tons
Class 5 Aggregate Base 26,166 Tons
Full Depth Reclamation 109,027 Sq. Yd.
Stabilized Full Depth Reclamation (Cement) 105,392 Sq. Yd.
Mill Bit. Surface 3.0” Depth 87,260 Sq. Yd.
2360 Plant Mixed Bituminous 35,900 Tons
4” Perf. PE Edge Drain 65,416 Lin. Ft.
Traffic Control 1 Lump Sum
Turf Establishment 1 Lump Sum
4" Solid & Broken Line Traffic Paint 108,945 Lin. Ft.

Proposals, plans, and specifications may be examined and obtained at the County Highway Engineer's Office, 88 South Park Avenue, Le Center, Minnesota 56057, telephone 507-357-8210. The price of plans is $25.00. A certified check or a corporate surety bond, made payable to the Treasurer of Le Sueur County, must accompany bids in an amount of not less than five percent (5%) of total bid.
The County Board reserves the right to reject any or all bids and to waive any defects therein.
Danielle Ongie
County Auditor
Le Sueur County, Minnesota
Project Major Items:
NumberItemUnitsQuantity
2211.509Aggregate Base CL. 5Ton26,166.00
2215.504Full Depth Reclamation 7.0" DepthSq.Yd.109,027.00
2215.504Stabilized Full Depth Reclamation 10.0" DepthSq. Yd.105,392.00
2221.509Shoulder Base Agg. CL. 1Ton12,000.00
2232.504Mill Bitum. Surface 3.0" DepthSq. Yd.87,260.00
2360.509Type SP 12.5 Non-Wear Course Mixture (3,C)Ton24,100.00
2360.509Type SP 9.5 Wear Course Mixture (3,C)Ton11,800.00
2502.6034" Perf. PE. Pipe DrainLin. Ft.65,416.00
2563.601Traffic ControlLump Sum1.00
2575.501Turf EstablishmentLump Sum1.00
2582.5034" Broken Line PaintLin. Ft.4,008.00
2582.5034" Solid Line PaintLin. Ft.104,937.00
Project Owner:

Le Sueur County Highway
88 South Park Ave
Le Center, MN   56057
(507) 357-8211
nolson@co.le-sueur.mn.us
Project Engineer:

Le Sueur County Highway
88 South Park Ave
Le Center, MN   56057
(507) 357-8211
nolson@co.le-sueur.mn.us