- Project Number:
- SAP 051-617-012
- Contract Number:
- 2302
- Other Project Numbers:
- SAP 051-622-009: SAP 051-622-009
SAP 051-608-020: SAP 051-608-020
SAP 051-642-020: SAP 051-642-020
SAP 051-645-008: SAP 051-645-008
SAP 064-605-034: SAP 064-605-034
- Project Description:
- Milling, Bituminous Overlay, Aggregate Shouldering
- Construction Location:
- In the Northeast corner of Murray County.
- City or Township:
- Bid Opening:
- 03/21/2023 9:00 AM
- Expected Award Date:
- 03/21/2023
- Project Start Date:
- 04/18/2023
- Construction Start Date:
- 04/18/2023
- Construction End Date:
- 08/26/2023
- Work Type:
- Surfacing
- Project Type:
- Road and Street
- Highest Funding Level:
- State
- DBE Project:
- No
To download the plan and proposal please go to the Murray County Website by clicking on the full ad link below or copy and paste the following address to your browser. http://hwy.murray-countymn.com/he/projects.asp
Project Major Items:
Number | Item | Units | Quantity |
---|
2232.504/00060 | MILL BITUMINOUS SURFACE (2") | SQ. YD. | 57,649.00 |
2360.509 | TYPE SP 12.5 BIT. MIXTURE FOR PATCHING (2,B) | TON | 6,425.00 |
2360.509/22200 | TYPE SP 12.5 WEARING COURSE MIXTURE (2,B) | TON | 36,345.00 |
2582.503/10104 | 4" SOLID LINE PAINT | LIN. FT. | 253,618.00 |
2582.503/10204 | 4" BROKEN LINE PAINT | LIN. FT. | 18,220.00 |