- Project Number:
- CP 71 604-021
- Contract Number:
- 21010
- Other Project Numbers:
- CP 71 604-021: CP 71-604-021
CP 71-609-021: CP 71-609-021
CP 71-613-021: CP 71-613-021
CP 71-661-019: CP 71-661-019
- Project Description:
- 2022 CSAH 4 Surface Improvements
- Construction Location:
- CSAH 4 from CSAH 5 to CSAH 15
- City or Township:
- Bid Opening:
- 03/09/2022 12:00 PM
- Expected Award Date:
- 03/22/2022
- Project Start Date:
- 05/16/2022
- Construction Start Date:
- 05/16/2022
- Construction End Date:
- 07/29/2022
- Work Type:
- Surfacing
- Project Type:
- Road and Street
- Highest Funding Level:
- Local
- DBE Project:
- No
ADVERTISEMENT FOR BIDS
CP 71-604-021 CSAH 4 from CSAH 5 to CSAH 15
CP 71-609-021 CSAH 9 from US Hwy 169 to CSAH 19
CP 71-613-021 CSAH 13 from CSAH 33 to E. Co. Line
CP 71-661-019 CR 61 from CSAH 20 to CSAH 3
SHERBURNE COUNTY, MINNESOTA
NOTICE is hereby given that electronic bids will be accepted through the Sherburne County online bid portal https://bidvault.mn.uccs.com/ until 12:00 PM on Wednesday, March 9, 2022 . This will be the only means of submittal of a bid.
The Major Quantities of Work are:
CONSTRUCT RIGHT TURN/BYPASS LANES EA 4
AGGREGATE BASE CLASS 5 TON 585
STABILIZED FULL DEPTH RECLAMATION SY 14,017
BITUMINOUS WEARING COURSE MIX TON 48,802
15” PIPE CULVERT LF 174
SEEDING AC 3
PAVEMENT MARKINGS LF 150,346
The bids will be reviewed by the County Engineer and County Attorney for the approval of the bid bond and the results of the review shall be posted within 3 business days at the following website: https://mn-co-sherburne.app.rtvision.com/oneoffice. Review of the bids by the County Engineer and the County Attorney should not be construed as an award of the bid. The final approval of the bid requires action by the County Board.
Plans & specifications may be examined at the office of the Sherburne County Highway Engineer, 13880 Business Center Drive Suite 100, Elk River MN 55330, Monday-Friday 8 am to 4:30 pm, or online at https://www.co.sherburne.mn.us/publicworks/index.php & follow the Construction Projects & Bids (eGram) link. A user ID & password is required to download the Plans & Specifications. Contact Public Works at 763-765-3300 to obtain the necessary information.
The advertisement for this project may also be viewed at the MnDOT State Aid for Local Transportation eAdvert web site at https://eadvert.rtvision.com
The cost to download the Plans & Specifications is free.
The cost to obtain a hard copy of the Plans & Specifications is $50.00 with an additional $10.00 mailing fee.
THE COST TO SUBMIT A BID WILL BE $25.00 PAYABLE TO RTVISION WHICH ALLOWS ACCESS TO THE ELECTRONIC BID DOCUMENTS VIA BID VAULT AT https://bidvault.mn.uccs.com
All bids shall be accompanied by a bid bond for at least five percent (5%) of the amount of the bid.
No bidder may withdraw their bid (which shall include the bid bond) within 15 days of the scheduled bid submittal date of Wednesday, March 9, 2022.
The County Board reserves the right to reject any or all bids and to waive minor irregularities. The County Board will consider award of the contract at the March 22, 2022 County Board Meeting contingent upon County Engineer & County Attorney review.
It is the County’s intent to begin construction the middle part of May 2022 and completed by end of July 2022 .
The County Board reserves the right to reject any or all bids & waive informalities.
Dated at Elk River Minnesota, this 7th day of February 2022.
Signed: Bruce Messelt, Sherburne County, Minnesota