- Project Number:
- 21-13
- Contract Number:
- 21-13
- Other Project Numbers:
- 21-13 21-13
- Project Description:
- Marion Street Pathway
- Construction Location:
- 2660 Civic Center Dr
- City or Township:
- Roseville
- Bid Opening:
- 08/17/2021 9:00 AM
- Expected Award Date:
- 08/23/2021
- Project Start Date:
- 08/18/2021
- Construction Start Date:
- 08/18/2021
- Construction End Date:
- 09/15/2021
- Work Type:
- Surfacing
- Project Type:
- Road and Street
- Highest Funding Level:
- Federal
- DBE Project:
- No
The Marion Street Pathway Project includes aggregate base, bituminous paving, concrete curb and gutter, concrete sidewalk work, signage and pavement markings.
Project Major Items:
Number | Item | Units | Quantity |
---|
2112.604/00010 | SUBGRADE PREPARATION | S Y | 1,050.00 |
2211.507/00170 | AGGREGATE BASE (CV) CLASS 5 | C Y | 170.00 |
2301.504/00060 | CONCRETE PAVEMENT 6" | S Y | 170.00 |
2360.501/0002 | TYPE SPWEA240B WEARING COURSE MIX PATHWAY | TON | 150.00 |
2531.503/02315 | CONCRETE CURB & GUTTER DESIGN B618 | L F | 60.00 |
2531.618/00010 | TRUNCATED DOMES | S F | 48.00 |
2582.518/06000 | CROSSWALK MULTI COMP | S F | 60.00 |