- Project Number:
- Project 2018DEVP-Z12
- Contract Number:
- Project 2018DEVP-Z12
- Other Project Numbers:
- 2018DEVP-Z12
- Project Description:
- Bluff View Street and Utility Improvements Project
- Construction Location:
- Bluff View Street and Utility Improvements Project
- City or Township:
- Northfield
- Bid Opening:
- 06/17/2021 2:00 PM
- Expected Award Date:
- 07/06/2021
- Project Start Date:
- 07/06/2021
- Construction Start Date:
- 07/06/2021
- Construction End Date:
- 06/15/2022
- Work Type:
- Water Main/Storm Sewer/Sanitary Sewer
- Project Type:
- Road and Street
- Highest Funding Level:
- Local
- DBE Project:
- No
The Bluff View Street and Utility Improvements Project (Attachment 3) includes an approximate 950’ extension of Ford Street, and an approximate 450’ extension of Aspen Street. The Development is proposed to have three (3) 4-plex townhome units, and 17 twin home units as part of the development.
Project Major Items:
Number | Item | Units | Quantity |
---|
2211.509/00070 | AGGREGATE BASE CLASS 5 | TON | 2,450.00 |
2360.509/13300 | TYPE SP 9.5 WEARING COURSE MIX (3;C) | TON | 1,150.00 |
2503.503/13080 | 8" PVC PIPE SEWER | L F | 453.00 |
2503.503/13120 | 12" PVC PIPE SEWER | L F | 851.00 |
2504.603/01082 | 8" WATERMAIN DUCTILE IRON CL 52 | L F | 430.00 |
2504.603/01122 | 12" WATERMAIN DUCTILE IRON CL 52 | L F | 845.00 |
2521.518/00040 | 4" CONCRETE WALK | S F | 9,000.00 |
2521.518/00115 | 1.5" BITUMINOUS WALK | S F | 22,500.00 |
2531.503/02315 | CONCRETE CURB & GUTTER DESIGN B618 | L F | 2,640.00 |