- Project Number:
- SAP 027-756-023
- Contract Number:
- Other Project Numbers:
- 4115600 & 2201300
- Project Description:
- Replacement of a storm sewer pipe running under CSAH 156. Additionally, pavement mill/overlay on the south side of the CP Rail crossing directly to the south of the project.
- Construction Location:
- CSAH 156 (Winnetka Avenue)
- City or Township:
- New Hope
- Bid Opening:
- 01/26/2021 2:00 PM
- Expected Award Date:
- 03/09/2021
- Project Start Date:
- 04/15/2021
- Construction Start Date:
- 04/15/2021
- Construction End Date:
- 11/30/2021
- Work Type:
- Pipe and Culvert
- Project Type:
- Drainage
- Highest Funding Level:
- State
- DBE Project:
- No