Minnesota County Engineers Association City Engineers Association of Minnesota Minnesota Department of Transportation
Home | Advanced Search | FAQ | Bid Calendar | Privacy Policy |
rss feed icon rss feed icon

Project Number:
SAP-039-594-001
Contract Number:
Other Project Numbers:
LOTW20205
Project Description:
Storm Sewer, Sanitary Sewer, Aggregate Base, Bituminous Surfacing, Concrete Curb and Gutter, Concrete Walks and Related Restoration on First Avenue NW between Main Street and 2nd Street NW.
Construction Location:
First Avenue NW
From Main Street to 2nd Street NW
City or Township:
Baudette
Bid Opening:
05/26/2020 12:00 PM
Expected Award Date:
06/02/2020
Project Start Date:
06/08/2020
Construction Start Date:
06/08/2020
Construction End Date:
09/15/2020
Work Type:
Reconstruct
Project Type:
Road and Street
Highest Funding Level:
Local
DBE Project:
No
Storm Sewer, Sanitary Sewer, Aggregate Base, Bituminous Surfacing, Concrete Curb and Gutter, Concrete Walks and Related Restoration on First Avenue NW between Main Street and 2nd Street NW.
Project Major Items:
NumberItemUnitsQuantity
4" SidewalkSF8,100.00
Bituminous Asphalt Ton1,080.00
Common Excavation CY7,700.00
Curb and GutterLF2,000.00
Sanitary SewerLF410.00
Storm SewerLF750.00
Project Owner:

Anthony Pirkl
306 8th Avenue Se
Baudette, MN   56623
(218) 434-0394
anthony_p@co.lotw.mn.us
anthony_p@co.lotw.mn.us
Project Engineer:

Anthony Pirkl
306 8th Avenue Se
Baudette, MN   56623
(218) 434-0394
anthony_p@co.lotw.mn.us
anthony_p@co.lotw.mn.us