Project Number:
SAP 045-611-007
Contract Number:
Other Project Numbers:
SAP 045-611-007
Project Description:
Bituminous Pavement Milling and Bituminous Surfacing
Construction Location:
City or Township:
Bid Opening:
08/20/2019 11:00 AM
Expected Award Date:
08/20/2019
Project Start Date:
09/10/2019
Construction Start Date:
09/10/2019
Construction End Date:
06/30/2020
Work Type:
Bituminous
Project Type:
Road and Street
Highest Funding Level:
State
DBE Project:
No
NOTICE TO CONTRACTORS

Sealed bids will be received until 11:00 AM on August 20, 2019, by Scott Peters, Marshall County Auditor, on behalf of the Marshall County Board of Commissioners for the project listed below:

BITUMINOUS PAVEMENT MILLING AND BITUMINOUS SURFACING

Project No. SAP 045-611-007

On CSAH 11, Between CSAH 2 and CSAH 28

Remove Bituminous Pavement: 8,576 SY
Shoulder Base Aggregate, CL I: 3,610 Ton
Mill Bituminous Surface (3.0"): 140,840 SY
Type SP 9.5 Wearing Course Mix: 25,124 Ton
RC Pipe: 361 LF
PVC Pipe Sewer: 1,025 LF
Concrete Curb & Gutter Design B624: 522 LF

lans, proposals, and specifications may be examined and secured at the Office of the Marshall County Highway Engineer; 447 So. Main; Warren, Minnesota 56762.

Over the counter Proposal and Plans are $45.00 per set including tax. Proposals and Plans not sold separately. No refunds will be made.

Digital Copies of the bidding documents are available at:
http://www.co.marshall.mn.us/departments/highway_department/index.php

These documents may be downloaded at https://egram.co.marshall.mn.us/ (Projects in Bidding). Bidders are responsible for all present and future downloads, including addendums and their attachments.

There is no cost to register or download the Project Plans and Proposal documents. To become a registered plan holder, you must create an account at: https://connex.mn.uccs.com.

Bids must be accompanied by a certified check made payable to the Marshall County Treasurer or a Corporate Surety Bond made in favor of Marshall County, Minnesota in an amount not less than five percent (5%) of the total bid.

Marshall County reserves the right to accept or reject any or all bids and waive any irregularities.

Scott Peters
County Auditor
Marshall County
Warren, MN 56762

Date: July 15, 2019
Project Owner:

Aune, Lon
447 South Main
Warren, MN   56762
(218) 745-4381
(218) 745-4570
lon.aune@co.marshall.mn.us
Project Engineer:

Aune, Lon
447 South Main
Warren, MN   56762
(218) 745-4381
(218) 745-4570