- Project Number:
- 06-2019
- Contract Number:
- 06-2019
- Other Project Numbers:
- Project Description:
- Bituminous Overlays
- Construction Location:
- City or Township:
- Bid Opening:
- 08/08/2019 1:00 PM
- Expected Award Date:
- 08/20/2019
- Project Start Date:
- 09/03/2019
- Construction Start Date:
- 09/03/2019
- Construction End Date:
- 09/18/2020
- Work Type:
- Bituminous
- Project Type:
- Road and Street
- Highest Funding Level:
- State
- DBE Project:
- No
Aggregate Shouldering and Bituminous Surfacing at the following locations:
SAP 041-602-011 - CSAH 2 between CSAH 9 & TH 14 (Length: 3.992 mi.)
SAP 041-608-037 - CSAH 8 between CSAH 13 & CSAH 15 (Length: 5.028 mi.)
SAP 041-611-012 - CSAH 11 between CSAH 8 & East County Line (Length: 2.024 mi.)
CP 000-129-019 - CR 129 between 3rd St in Verdi & CSAH 9 (Length: 0.185 mi.)
County Maintenance CSAH 8- CSAH 8 between 300th St & 290th St (Length: 0.014 mi.)
Plans, proposals and specifications may be obtained online at http://www.co.lincoln.mn.us/Departments/Highway.htm ,
or at the Lincoln County Highway Department Offce
Electronic copies of the plans, proposals and specifications will be available for free online.
Hard copies will have a non-refundable charge of $100.00 (includes shipping and tax) for each set.
Project Major Items:
Number | Item | Units | Quantity |
---|
2221.509 | Shoulder Base Aggregate | Ton | 4,340.00 |
2232.504 | Mill Bituminous Surface | Sq Yd | 56,397.00 |
2360.509 | Type SP 12.5 Wearing Course Mixture (2,B0 | Ton | 13,829.00 |
2582.503 | 4" Solid Line Paint | Lin Ft | 165,552.00 |