- Project Number:
- SAP 086-592-001
- Contract Number:
- 1906
- Other Project Numbers:
- Project Description:
- 150th Street reconstruction from Grover Avenue to Endicott Avenue in Clearwater/Silver Creek Townships.
- Construction Location:
- City or Township:
- Clearwater/Silver Creek Twp
- Bid Opening:
- 04/19/2019 11:00 AM
- Expected Award Date:
- 04/30/2019
- Project Start Date:
- 05/20/2019
- Construction Start Date:
- 05/20/2019
- Construction End Date:
- 08/31/2019
- Work Type:
- Reconstruct
- Project Type:
- Road and Street
- Highest Funding Level:
- State
- DBE Project:
- No
Sealed Bids for the 150th Street Reconstruction Project (S.A.P. 086-592-001) will be received by the Wright County Highway Department @ 3600 Braddock Av NE, Buffalo, MN, until 11:00 a.m. Friday, April 19th, 2019, at which time the bids received will be publicly opened and read aloud.