- Project Number:
- CP 19-100
- Contract Number:
- Other Project Numbers:
- Project Description:
- CP 19-100 Pavement Markings
- Construction Location:
- County Wide
- City or Township:
- Bagley
- Bid Opening:
- 04/09/2019 10:00 AM
- Expected Award Date:
- 04/09/2019
- Project Start Date:
- 04/16/2019
- Construction Start Date:
- 06/01/2019
- Construction End Date:
- 09/30/2019
- Work Type:
- Traffic Marking/Striping
- Project Type:
- Road and Street
- Highest Funding Level:
- Local
- DBE Project:
- No
NOTICE TO CONTRACTORS: Sealed proposals will be received until 10:10 A.M. on April 9, 2019 by Allen Paulson, Clearwater County Auditor, County Courthouse, 213 Main Avenue N., Dept. 202, Bagley, MN 56621-8304, on behalf of the Clearwater County Board of Commissioners for the County Project listed below. Proposals will be opened and read publicly at the County Courthouse in Bagley, MN immediately after the hour set for receiving bids.
CP 19-100 PAVEMENT MARKINGS
Work consists of highway centerline striping and 4" edgeline striping on approximately 105 road miles and 6" edgeline striping on approximately 5 road miles of Clearwater County roads. Work shall be completed by September 30, 2019.
Proposals and specifications may be examined and secured at the Office of the County Engineer, 113 7th St. NE, Bagley, MN 56621-9103, (218) 694-6132 or by sending your name, address, phone number, fax number, e-mail address and project name & number to
char.shafer@co.clearwater.mn.us
Project Major Items:
Number | Item | Units | Quantity |
---|
2582.504 | 4" White Paint | Gallons | 3,048.00 |
2582.504 | 4" Yellow Paint | Gallons | 1,498.00 |
2582.504 | 6" White Paint | Gallons | 225.00 |