- Project Number:
- 19-04
- Contract Number:
- 19-04
- Other Project Numbers:
- 19-04
- Project Description:
- 2019 PMP Street Maintenance
- Construction Location:
- City or Township:
- Bid Opening:
- 03/19/2019 1:00 PM
- Expected Award Date:
- 03/25/2019
- Project Start Date:
- 06/01/2019
- Construction Start Date:
- 06/01/2019
- Construction End Date:
- 10/18/2019
- Work Type:
- Bituminous
- Project Type:
- Maintenance
- Highest Funding Level:
- Local
- DBE Project:
- No
2019 Pavement Management Project
Project Major Items:
Number | Item | Units | Quantity |
---|
2232.504 | MILL BITUMINOUS SURFACE (1.5") | S Y | 88,968.00 |
2232.504 | MILL BITUMINOUS SURFACE (2.0") | S Y | 52,252.00 |
2360.509 | TYPE SP 9.5 WEARING COURSE MIX (3;B) | TON | 12,786.00 |
2504.603 | 8" WATERMAIN HDPE (DIRECTIONAL DRILLED) | L F | 650.00 |
2531.503 | CONCRETE CURB & GUTTER DESIGN B618 | L F | 2,888.00 |
2565.616 | REVISE SIGNAL SYSTEM | SYS | 1.00 |