- Project Number:
- SAP 034-599-039
- Contract Number:
- Other Project Numbers:
- Project Description:
- Bridge Replacement No. 34J49 located on 120th Street NW approximately 1.2 miles south of CSAH 27. (Mamre Township)
- Construction Location:
- City or Township:
- Bid Opening:
- 03/19/2019 10:00 AM
- Expected Award Date:
- 03/19/2019
- Project Start Date:
- 05/01/2019
- Construction Start Date:
- 05/01/2019
- Construction End Date:
- 08/31/2019
- Work Type:
- Pipe and Culvert
- Project Type:
- Bridges
- Highest Funding Level:
- State
- DBE Project:
- No
Combined estimated quantities of work are: 10â™x6â™ Precast Conc Box Culvert â" 88 LIN FT, 10â™x 6â™ Precast Concrete Box Culvert End Sections â" 2 EACH, 15❠CS Pipe Culvert (Riveted) â" 168 LIN FT, 15❠GS Pipe Apron â" 2 EACH, Remove Old Bridge â" 1 LUMP SUM, Aggregate Surfacing Class 5 â" 490 TON, Common Borrow (LV) â" 1323 CU YD, Remove Pipe Culvert â" 86 LIN FT, Aggregate Backfill (CV) (P) â" 83 CU YD, Random Riprap Class 3 (Quarry-run) â" 551 CU YD, Turf Establishment and other miscellaneous construction items.