Number | Item | Units | Quantity |
---|
2021.501 | MOBILIZATION | LUMP SUM | 1.00 |
2021.601 | RAILROAD PROTECTIVE SERVICES | LUMP SUM | 1.00 |
2101.524 | CLEARING | TREE | 13.00 |
2101.524 | GRUBBING | TREE | 13.00 |
2104.502 | REMOVE CASTING | EACH | 13.00 |
2104.502 | REMOVE HANDHOLE | EACH | 10.00 |
2104.502 | REMOVE LIGHT FOUNDATION | EACH | 20.00 |
2104.502 | REMOVE SIGN TYPE C | EACH | 17.00 |
2104.502 | SALVAGE LIGHTING UNIT | EACH | 20.00 |
2104.503 | REMOVE CURB & GUTTER | LIN FT | 601.00 |
2104.503 | REMOVE UNDERGROUND WIRE | LIN FT | 2,821.00 |
2104.503 | SAWING BIT PAVEMENT (FULL DEPTH) | LIN FT | 820.00 |
2104.503 | SAWING BITUMINOUS PAVEMENT | LIN FT | 328.00 |
2104.503 | SAWING CONCRETE PAVEMENT (FULL DEPTH) | LIN FT | 233.00 |
2104.504 | REMOVE BITUMINOUS PAVEMENT | SQ YD | 310.00 |
2104.504 | REMOVE CONCRETE DRIVEWAY PAVEMENT | SQ YD | 183.00 |
2104.518 | REMOVE CONCRETE SIDEWALK | SQ FT | 10,106.00 |
2104.602 | REMOVE RECEPTACLE STANCHION | EACH | 10.00 |
2106.507 | COMMON EMBANKMENT (CV) | CU YD | 6.00 |
2106.507 | EXCAVATION - COMMON | CU YD | 275.00 |
2118.509 | AGGREGATE SURFACING CLASS 5 | TON | 8.00 |
2123.510 | 0.5 CU YD SHOVEL | HOUR | 8.00 |
2123.510 | 12 CU YD TRUCK | HOUR | 8.00 |
2123.510 | 4.0 CU YD FRONT END LOADER | HOUR | 8.00 |
2211.509 | AGGREGATE BASE CLASS 5 | TON | 370.00 |
2232.504 | MILL BITUMINOUS SURFACE (2.0") | SQ YD | 4,579.00 |
2357.506 | BITUMINOUS MATERIAL FOR TACK COAT | GALLON | 438.00 |
2360.509 | TYPE SP 9.5 BIT MIXTURE FOR ENTRANCES (3,B) | TON | 33.00 |
2360.509 | TYPE SP 9.5 WEARING COURSE MIX (3;B) | TON | 633.00 |
2504.602 | ADJUST CURB STOP | EACH | 12.00 |
2504.602 | ADJUST VALVE BOX | EACH | 1.00 |
2504.602 | ADJUST VALVE BOX (SPECIAL) | EACH | 4.00 |
2506.502 | CASTING ASSEMBLY | EACH | 13.00 |
2506.602 | ADJUST FRAME & RING CASTING (SPECIAL) | EACH | 3.00 |
2506.602 | CASTING ASSEMBLY SPECIAL | EACH | 1.00 |
2506.602 | REPAIR DRAINAGE STRUCTURE | EACH | 10.00 |
2521.518 | 6" CONCRETE WALK | SQ FT | 9,506.00 |
2531.503 | CONCRETE CURB & GUTTER DESIGN B624 | LIN FT | 587.00 |
2531.504 | 7" CONCRETE DRIVEWAY PAVEMENT | SQ YD | 181.00 |
2531.618 | TRUNCATED DOMES | SQ FT | 126.00 |
2540.602 | RECEPTACLE STANCHION | EACH | 9.00 |
2545.502 | EQUIPMENT PAD | EACH | 1.00 |
2545.502 | HANDHOLE | EACH | 4.00 |
2545.502 | LIGHT FOUNDATION DESIGN E MODIFIED | EACH | 15.00 |
2545.502 | SERVICE CABINET | EACH | 1.00 |
2545.502 | SERVICE EQUIPMENT | EACH | 1.00 |
2545.503 | 0.75" NON-METALLIC CONDUIT | LIN FT | 281.00 |
2545.503 | 2" NON-METALLIC COND (DIRECTIONAL BORE) | LIN FT | 182.00 |
2545.503 | 2" NON-METALLIC CONDUIT | LIN FT | 1,464.00 |
2545.503 | UNDERGROUND WIRE 1/C 10 AWG | LIN FT | 1,113.00 |
2545.503 | UNDERGROUND WIRE 1/C 2 AWG | LIN FT | 4,869.00 |
2545.503 | UNDERGROUND WIRE 1/C 6 AWG | LIN FT | 7,536.00 |
2545.503 | UNDERGROUND WIRE 1/C 8 AWG | LIN FT | 6,126.00 |
2545.503 | UNDERGROUND WIRE 1 COND 12 AWG | LIN FT | 2,680.00 |
2545.602 | INSTALL LIGHTING UNIT | EACH | 15.00 |
2563.601 | TRAFFIC CONTROL | LUMP SUM | 1.00 |
2564.618 | SIGN TYPE C | SQ FT | 84.89 |
2571.524 | DECIDUOUS TREE 2" CAL B&B | TREE | 9.00 |
2573.502 | STORM DRAIN INLET PROTECTION | EACH | 15.00 |
2573.503 | SEDIMENT CONTROL LOG TYPE STRAW | LIN FT | 609.00 |
2574.507 | COMMON TOPSOIL BORROW | CU YD | 15.00 |
2574.508 | FERTILIZER TYPE 3 | POUND | 14.00 |
2575.504 | RAPID STABILIZATION METHOD 4 | SQ YD | 50.00 |
2575.504 | SODDING TYPE LAWN | SQ YD | 174.00 |
2580.503 | INTERIM PAVEMENT MARKING | LIN FT | 3,544.00 |
2582.503 | 24" SOLID LINE PREF TAPE GR IN (WR) | LIN FT | 82.00 |
2582.503 | 4" DBLE SOLID LINE MULTI COMP GR IN (WR) | LIN FT | 886.00 |
2582.503 | 6" SOLID LINE MULTI COMP GR IN (WR) | LIN FT | 1,377.00 |
2582.518 | CROSSWALK PREF TAPE GR IN (WR) | SQ FT | 432.00 |
2582.518 | PAVT MSSG PREF TAPE GR IN (WR) | SQ FT | 123.44 |