Project Number:
SAP 086-618-012
Contract Number:
1807
Other Project Numbers:
CP 86-18-171 SAP 086-618-012
Project Description:
Reconstruct: CSAH 18 from Maciver Ave to Naber Ave NE
Construction Location:
City or Township:
Bid Opening:
05/10/2018 11:00 AM
Expected Award Date:
05/29/2018
Project Start Date:
06/18/2018
Construction Start Date:
06/18/2018
Construction End Date:
10/26/2018
Work Type:
Reconstruct
Project Type:
Road and Street
Highest Funding Level:
State
DBE Project:
No
Advertisement for Bids: Notice is hereby given that electronic bids will be accepted by the County Engineer until 11:00 a.m. Thursday, May 10, 2018 for the contract listed below:
Contract Number 1807, CSAH 18 Construction Project (SAP 086-618-012, CP 86-18-171, etc.):
Reconstruction of approximately 1.4 mi of CSAH 18 from MacIver Ave to CSAH 22 (Naber Ave), Roundabout construction at CSAH 18 & MacIver Ave/Barthel Industrial Drive, CSAH 18 & CSAH 22. Two alternates for 600 foot long soil correction area; muck excavation & replacement, surcharge.
Project Owner:

Hawkins, Virgil G
3600 Braddock Avenue NE
Buffalo, MN   55313
(763) 682-7383
(763) 682-7313
virgil.hawkins@co.wright.mn.us
Project Engineer:

Hausmann, Chad D
3600 Braddock Avenue NE
Buffalo, MN   55313
(763) 682-7383
(763) 682-7313
chad.hausmann@co.wright.mn.us