- Project Number:
- SAP 023-599-198
- Contract Number:
- Other Project Numbers:
- Project Description:
- Bridge replacement with culvert and approach grading
- Construction Location:
- located on 160th St, 2.34 miles west of intersection of CSAH 5/160th St
approx. 6.5 miles SE of Ostrander, MN
- City or Township:
- Cherry Grove, MN
- Bid Opening:
- 05/14/2018 1:30 PM
- Expected Award Date:
- 05/22/2018
- Project Start Date:
- 07/09/2018
- Construction Start Date:
- 07/09/2018
- Construction End Date:
- 11/02/2018
- Work Type:
- Pipe and Culvert
- Project Type:
- Bridges
- Highest Funding Level:
- State
- DBE Project:
- No
Notice is hereby given that sealed bids will be accepted by the County Engineer, at the Fillmore County Highway Department, Preston, MN until 1:30 p.m. on the 14th day of May, 2018, for the following project:
SAP 023-599-198: Bridge replacement with culvert and approach grading, located on 160th St (Twp 381), from the intersection of CSAH 5 and 160th St in Cherry Grove, MN west on 160th St 2.34 miles, approximately 6.5 miles SE of Ostrander, MN. Major quantities include 10' X 5' pc concrete box culvert & end sections, excavation, aggregate and erosion control.
Plan and proposal price is $30.00 picked up, and $35.00 if sent by US mail.
Project Major Items:
Number | Item | Units | Quantity |
---|
2104.503 | Remove Pipe Culvert | LF | 195.00 |
2106.507 | Excavation-Common | CY | 1,533.00 |
2118.509 | Aggregate Surface Cl 2 | Ton | 118.00 |
2412.502 | 10 X 5 PC Conc Box Culvert End Section Type 1 | Each | 4.00 |
2412.503 | 10 X 5 PC Conc Box Culvert Cl 1 | LF | 72.00 |
2442.501 | Remove Existing Bridge | LS | 1.00 |
2511.509 | Random Riprap Class V | Ton | 237.00 |
2575.504 | Erosion Control Blanket, Cat 3 Straw 2S | SY | 1,779.00 |