Minnesota County Engineers Association City Engineers Association of Minnesota Minnesota Department of Transportation
Home | Advanced Search | FAQ | Bid Calendar | Privacy Policy |
rss feed icon rss feed icon

Project Number:
CSAH 5 & CSAH 8 Bit Reclaim & Bit Surfacing & Culv
Contract Number:
Winona County
Other Project Numbers:
CP 1505 SAPs 085-605-022 & 085-608-009
Project Description:
CR 5 & CR 8 - BITUMINOUS RECLAMATION, BITUMINOUS SURFACING, EXCAVATION, CULVERT REPLACEMENTS & AGGREGATE SHOULDERING

Includes Base & Shouldering, Culvert/Cattle Pass Removals, Culverts & Aprons, Riprap, Traffic Control, Turf Establishment & Striping
Construction Location:
CSAH 5 from JCT CR 125 to 3.19 Miles South
CSAH 8 from JCT CR 11 to 1.58 Miles East
City or Township:
Pleasant Hill & New Hartford
Bid Opening:
03/19/2018 1:00 PM
Expected Award Date:
03/27/2018
Project Start Date:
04/16/2018
Construction Start Date:
04/16/2018
Construction End Date:
10/26/2018
Work Type:
Surfacing
Project Type:
Road and Street
Highest Funding Level:
State
DBE Project:
No
ESTIMATED QUANTITIES OF WORK
Mobilization - 2 LS
Salvage RC Cattle Pass - 6 LF
Salvage Cattle Pass Apron - 2 Each
Remove Pipe Culvert & Cattle Pass - 606 LF
Remove Traffic Barrier - 1,195 LF
Common Excavation - 1,048 CY
Aggregate Shoulder Surfacing & Base Class 2 & Class 2 Modified - 3,311; Ton
Dozer - 10 Hour
Full Depth Bituminous Pavement Reclamation - 62,563 SY
Mill Bituminous Surface - 482 SY
Type SP 12.5 Wearing Course Mix (2,C) - 15,529 Ton
Pavement Density Incentive - 2 LS
Pavement Smoothness Incentive - 78 Seg
Granular Backfill - 13,009 Ton
Granular Foundation and/or Bedding - 718 Ton
CS Pipe Apron 36" - 1 Each
RC Pipe Apron 24"-48" - 16 Each
72" High RC Cattle Pass Apron - 4 Each
Install RC Cattle Pass Apron - 2 Each
RC Pipe Culvert 24"-48" - 536 LF
72" High RC Cattle Pass Culvert - 90 LF
Install RC Cattle Pass - 6 LF
Pipe Ties (Hideaway Tie Rod & Single Connection Tie Bar) - 14 Each
Clean Pipe Culvert - 1 Each
Random Riprap Class III - 200 CY
4" Concrete Walk Special - 120 SF
End Treatment-Energy Absorbing Terminal - 3 Each
Install Traffic Barrier Design B8338 - 1,412.5 LF
Install Flared End Section - 1 Each
Traffic Control - 2 LS; Silt Fence Type MS - 1,100 LF
Fertilizer Type 3 - 375 LB
Erosion Control Blanket Cat 3N - 900 SY
Seeding - 1.07 Acres
Seed Mixture 25-141 - 80 LB
Hydraulic Stabilized Fiber Matrix - 3,331 SY
Roadway Striping - 75,147 L
and Miscellaneous and Appurtenant Items required for a Complete Project.
Project Owner:

Winona County Highway Department
5300 Highway 61 West
Winona, MN   55987
(507) 457-8840
(507) 454-3699
bspalding@co.winona.mn.us
Project Engineer:

Troy Drath, PE
Winona County Highway Department
5300 Highway 61 West
Winona, MN   55987
(507) 457-8840
(507) 454-3699
tdrath@co.winona.mn.us