- Project Number:
- 063-090-001
- Contract Number:
- Other Project Numbers:
- QuestCDN No. 8652750
- Project Description:
- work consists of the rehabilitation and reconstruction of approximately 3.2 miles of an asphalt multi-use path.
- Construction Location:
- Red Lake Falls
- City or Township:
- Red Lake Falls
- Bid Opening:
- 09/21/2023 3:30 PM
- Expected Award Date:
- 09/25/2023
- Project Start Date:
- 05/01/2024
- Construction Start Date:
- 05/01/2024
- Construction End Date:
- 09/27/2024
- Work Type:
- Trail Construction
- Project Type:
- Parks and Recreation
- Highest Funding Level:
- Local
- DBE Project:
- No
Electronic Bids will be received by the City of Red Lake Falls, Minnesota, on the QuestCDN.com website via the VirtuBid electronic bidding application. Only electronic bids will be accepted for this project. Bids will be received on the QuestCDN.com website, until 3:30 P.M., on Thursday, September 21st, 2023, at which time they will be opened electronically and reviewed for the furnishing of all labor, materials, and all else necessary for the following:
Bottineau Trail Improvements
In general and pursuant to Minnesota Statutes, chapter 429, the work consists of the rehabilitation and reconstruction of approximately 3.2 miles of an asphalt multi-use path. The work will generally include reconstruction of the trail and ADA improvements of the crossings of the trail.
Complete digital Bidding Documents are available at www.questcdn.com by inputting QuestCDN eBidDoc #8652750 on the website’s Project Search page.
Direct inquiries to Engineer’s Project Manager, Cavin Berube, at (701) 429-3110 and cavin.berube@stantec.com.