Minnesota County Engineers Association City Engineers Association of Minnesota Minnesota Department of Transportation
Home | Advanced Search | FAQ | Bid Calendar | Privacy Policy |
rss feed icon rss feed icon

Project Number:
County Wide Striping 2023
Contract Number:
Other Project Numbers:
Project Description:
County Wide Maintenance Striping
Construction Location:
County Wide
City or Township:
Bid Opening:
04/05/2023 1:00 PM
Expected Award Date:
04/18/2023
Project Start Date:
08/07/2023
Construction Start Date:
08/07/2023
Construction End Date:
08/30/2023
Work Type:
Traffic Marking/Striping
Project Type:
Road and Street
Highest Funding Level:
Local
DBE Project:
No
NOTICE

NOTICE TO CONTRACTORS - Sealed bids will be received until 1:00 p.m., Wednesday, April 5th, 2023, by Danielle Ongie, County Auditor of Le Sueur County, 88 South park Avenue, Le Center, Minnesota on behalf of the County Board of Commissioners for the centerline and edge line striping on 305.5 miles of county roadways.

The approximate major quantities are as follows:
4 inch Wide White Edge Stripe 10373 gallons
4 inch Wide Yellow Centerline Skips and No Passing Zones 6110 gallons

Specifications and special provisions may be obtained at the County Highway Engineer's Office, 88 South Park Avenue, Le Center, Minnesota 56057, telephone 507-357-8210.

A certified check or a corporate surety bond, made payable to the Treasurer of Le Sueur County, must accompany bids in an amount of not less than five percent (5%) of total bid.

The County Board reserves the right to reject any or all bids and to waive any defects therein.

Danielle Ongie
County Auditor
Le Sueur County, Minnesota
Project Major Items:
NumberItemUnitsQuantity
2582.5064" Broken & Solid Line Yellow PaintGAL6,110.00
2582.5064" Solid Line White PaintGAL10,373.00
Project Owner:

Le Sueur County Highway
88 South Park Ave
Le Center, MN   56057
(507) 357-8211
nolson@co.le-sueur.mn.us
Project Engineer:

Nathan Olson
88 South Park Ave
Le Center, MN   56057
(507) 357-8211
nolson@co.le-sueur.mn.us