- Project Number:
- LOST 112P-1
- Contract Number:
- Other Project Numbers:
- Project Description:
- Full depth reclamation, bituminous surfacing and aggregate shouldering
- Construction Location:
- approximately 5.5 miles NE of Mabel, MN on CR 112 beginning at the Jct of CSAH 18 and ending at the intersection of Aurora Rd
- City or Township:
- Preble Twp
- Bid Opening:
- 02/13/2023 2:00 PM
- Expected Award Date:
- 02/14/2023
- Project Start Date:
- 09/18/2023
- Construction Start Date:
- 09/18/2023
- Construction End Date:
- 10/13/2023
- Work Type:
- Surfacing
- Project Type:
- Road and Street
- Highest Funding Level:
- Local
- DBE Project:
- No
LOST 112P-1: Full Depth Reclamation, Bituminous Surfacing and Aggregate Shouldering, located approximately 5.5 miles NE of Mabel, MN on CR 112 beginning at the Jct of CSAH 18 and ending at the intersection of Aurora Rd. This project is funded by Fillmore County “Local Option Sales Tax” and therefore prevailing wages will not be required.
Plan and proposal price is $25.00 picked up, and $30.00 if sent by US mail.
Project Major Items:
Number | Item | Units | Quantity |
---|
2021.501 | Mobilization | LS | 1.00 |
2104.503 | Sawing Bituminous Pavement (Full Depth) | LF | 24.00 |
2106.507 | Excavation-Subgrade | CY | 50.00 |
2118.509 | Aggregate Surface Cl 2 | Ton | 2,318.00 |
2211.509 | Aggregate Base Class 2A Mod | Ton | 90.00 |
2215.504 | Full Depth Reclamation (P) | SY | 30,614.00 |
2360.509 | Type 12.5 Wearing Course Mix (3,C) | Ton | 7,732.00 |
2563.601 | Traffic Control | LS | 1.00 |
2582.503 | 4" Broken Line Paint | LF | 1,410.00 |
2582.503 | 4" Double Solid Line Paint | LF | 4,055.00 |
2582.503 | 4" Solid Line Paint | LF | 28,215.00 |