- Project Number:
- CP 7992-398713
- Contract Number:
- CP 7992-398713
- Other Project Numbers:
- CP 7992-398713: SAP 069-599-049
- Project Description:
- CP 7992-398713, SAP 069-599-049 (Br 777)
- Construction Location:
- 0.7 Mi. E of JCT of TH 53 on Twp. Rd 7992 over Pelican River 1.4 Mi SE of Orr, MN
- City or Township:
- Bid Opening:
- 10/27/2022 10:00 AM
- Expected Award Date:
- 11/15/2022
- Project Start Date:
- 12/01/2022
- Construction Start Date:
- 07/10/2023
- Construction End Date:
- 10/28/2023
- Work Type:
- Bridge
- Project Type:
- Bridges
- Highest Funding Level:
- State
- DBE Project:
- No
Bridge construction project on TWP 7992 (Johnson Rd), crossing Pelican River, and 1.5 miles SE of Orr, MN. New bridge to be constructed adjacent to the existing bridge structure in order to utilize the existing bridge as a bypass road during construction.
Project Major Items:
Number | Item | Units | Quantity |
---|
2106.507/00010 | EXCAVATION - COMMON | CU YD | 3,299.00 |
2401.507/03643 | STRUCTURAL CONCRETE (3B52) | CU YD | 58.00 |
2401.508/00011 | REINFORCEMENT BARS (EPOXY COATED) | POUND | 28,550.00 |
2401.518/03642 | BRIDGE SLAB CONCRETE (3Y42-M) | SQ FT | 2,695.00 |
2405.503/00030 | PRESTRESSED CONCRETE BEAMS 30MH | LIN FT | 344.00 |