- Project Number:
- 22-24
- Contract Number:
- 22-24
- Other Project Numbers:
- Project Description:
- 215th Street Extension, Galway Lane, and 220th Street Improvements
- Construction Location:
- East of Cedar Avenue, along 215th Street
- City or Township:
- Lakeville
- Bid Opening:
- 07/15/2022 10:30 AM
- Expected Award Date:
- 08/01/2022
- Project Start Date:
- 08/01/2022
- Construction Start Date:
- 08/01/2022
- Construction End Date:
- 09/30/2023
- Work Type:
- Bituminous
- Project Type:
- Road and Street
- Highest Funding Level:
- Local
- DBE Project:
- No
Construction of 215th Street, Galway Lane and 220th Street in Lakeville MN. Project includes roadway grading, paving, curb, storm sewer, sanitary sewer, watermain and precast concrete box culverts.
Project Major Items:
Number | Item | Units | Quantity |
---|
2106.507 | EXCAVATION - COMMON | CU YD | 65,625.00 |
2106.507 | SELECT GRANULAR EMBANKMENT (CV) (P) | CU YD | 17,522.00 |
2211.507 | AGGREGATE BASE CLASS 5 (P) | CU YD | 6,695.00 |
2360.509 | TYPE SP 12.5 NON WEAR COURSE MIX (3;C) | TON | 2,865.00 |
2360.509 | TYPE SP 12.5 NON WEAR COURSE MIX (4;B) | TON | 1,550.00 |
2360.509 | TYPE SP 12.5 WEARING COURSE MIX (4;E) | TON | 2,050.00 |
2360.509 | TYPE SP 9.5 WEARING COURSE MIX (3;C) | TON | 1,075.00 |
2412.503 | 14X6 PRECAST CONCRETE BOX CULVERT | LIN FT | 124.00 |
2412.503 | 14X8 PRECAST CONCRETE BOX CULVERT | LIN FT | 122.00 |
2501.503 | 15" RC PIPE CULVERT CLASS V | LIN FT | 360.00 |
2503.503 | 15" RC PIPE SEWER CLASS V | LIN FT | 2,108.00 |
2503.503 | 8" PVC PIPE SEWER (SDR 26) | LIN FT | 1,822.00 |
2504.603 | 12" PVC WATERMAIN (C900) | LIN FT | 4,110.00 |