- Project Number:
- 21-12
- Contract Number:
- 2022-03
- Other Project Numbers:
- Project Description:
- North Brainerd Reconstruction
- Construction Location:
- Juniper Street - N 2nd Street to N 10th Street, N 3rd Street - Washington Street to Holly Street, N 6th Street - Washington Street to Juniper Street, N 7th Street - Kingwood Street to Holly Street
- City or Township:
- Brainerd
- Bid Opening:
- 05/06/2022 10:00 AM
- Expected Award Date:
- 05/16/2022
- Project Start Date:
- 05/30/2022
- Construction Start Date:
- 05/30/2022
- Construction End Date:
- 10/14/2022
- Work Type:
- Reconstruct
- Project Type:
- Road and Street
- Highest Funding Level:
- Local
- DBE Project:
- No
ADVERTISEMENT FOR BIDS
CITY OF BRAINERD
BRAINERD, MINNESOTA
NORTH BRAINERD RECONSTRUCTION
General Notice
The City of Brainerd (Owner) is requesting Bids for the construction of the following Projects:
Imp. 21-12 North Brainerd Reconstruction
Bids for the construction of the Projects will be received at the Office of the City Engineer located at City of Brainerd, 501 Laurel Street, Brainerd, MN 56401, until Friday, May 6th, 2022 at 10:00 AM local time. At that time the Bids received will be publicly opened and read.
The Projects include the following Work:
Grading, Aggregate Base, Bituminous, Storm Sewer, Watermain, Concrete Curb & Gutter, Sidewalk and ADA Improvements.
Bids are requested for the following Contract: 2022-03
Obtaining the Bidding Documents
Information and Bidding Documents for the Project can be found at the following designated website:
https://mn-ci-brainerd.app.rtvision.com/oneoffice