- Project Number:
- R0896 CVT 025-2022-001
- Contract Number:
- 11301
- Other Project Numbers:
- R0897 CVT 025-2022-001
R0899 CVT 025-2022-001
R0900 CVT 025-2022-001
- Project Description:
- Bridge R0896 - Cannon Valley Trail
- Construction Location:
- in Goodhue County on the Cannon Valley Trail
- City or Township:
- Bid Opening:
- 04/26/2022 10:00 AM
- Expected Award Date:
- 05/03/2022
- Project Start Date:
- 11/01/2022
- Construction Start Date:
- 11/01/2022
- Construction End Date:
- 05/19/2023
- Work Type:
- Bridge
- Project Type:
- Bridges
- Highest Funding Level:
- Local
- DBE Project:
- No
Bridge Construction and Box Culvert Construction
Project Major Items:
Number | Item | Units | Quantity |
---|
2100.601/00016 | PEDESTRIAN BRIDGE (SUPERSTRUCTURE) | LS | 1.00 |
2412.503 | 14X4 PRECAST CONCRETE BOX CULVERT | EACH | 24.00 |
2412.503 | 16X4 PRECAST CONCRETE BOX CULVERT | LF | 23.00 |
2412.503/12040 | 12X4 PRECAST CONCRETE BOX CULVERT | L F | 21.00 |