- Project Number:
- CP 22-100
- Contract Number:
- Other Project Numbers:
- Project Description:
- Pavement Markings
- Construction Location:
- County Wide
- City or Township:
- Bagley
- Bid Opening:
- 04/12/2022 10:00 AM
- Expected Award Date:
- 04/12/2022
- Project Start Date:
- 04/12/2022
- Construction Start Date:
- 06/01/2022
- Construction End Date:
- 09/30/2022
- Work Type:
- Traffic Marking/Striping
- Project Type:
- Road and Street
- Highest Funding Level:
- Local
- DBE Project:
- No
Work consists of highway centerline striping on approximately 153 miles, 4” edgeline striping on approximately 35 road miles and 6” edgeline striping on approximately 37 road miles of Clearwater County roads. Work shall be completed by September 30, 2022.
Project Major Items:
Number | Item | Units | Quantity |
---|
2582.504 | Linear Marking 4 inch White | Gallon | 1,161.00 |
2582.504 | Linear Marking 4 inch Yellow | Gallon | 2,484.00 |
2582.504 | Linear Marking 6 inch White | Gallon | 1,841.00 |