Minnesota County Engineers Association City Engineers Association of Minnesota Minnesota Department of Transportation
Home | Advanced Search | FAQ | Bid Calendar | Privacy Policy |
rss feed icon rss feed icon

Project Number:
2183335
Contract Number:
2183335
Other Project Numbers:
Project Description:
Drainage Replacement and Realignment along Excelsior Blvd and Woodland Road in the city of Minnetonka.
Construction Location:
Near the corner of Excelsior Blvd and Woodland Road
City or Township:
Minnetonka
Bid Opening:
03/29/2022 2:00 PM
Expected Award Date:
05/20/2022
Project Start Date:
05/31/2022
Construction Start Date:
05/31/2022
Construction End Date:
07/09/2022
Work Type:
Water Main/Storm Sewer/Sanitary Sewer
Project Type:
Drainage
Highest Funding Level:
Local
DBE Project:
No
ADVERTISEMENT FOR BIDS

CSAH 3 Drainage at Woodland Road
C.P. 2183335;
BIDS CLOSE: 2:00 P.M., TUESDAY, March 29, 2022
HENNEPIN COUNTY, MINNESOTA

Electronic bids for the above referenced project will be accepted through Hennepin County’s online electronic bid system (ProcureWare) until 2:00 p.m., Tuesday, March 29, 2022, at which time they will be publicly opened by the Hennepin County Purchasing and Contract Services office. Bid results will be posted immediately after opening on Hennepin County’s ProcureWare website.

Location: CSAH 3 at Woodland Road in Minnetonka.

The major items of work are approximately: 1 LUMP SUM MOBILIZATION; 6 EACH REMOVE DRAINAGE STRUCTURE; 2 EACH SALVAGE CASTING; 1 EACH SALVAGE PEDESTRIAN PUSH BUTTON STATION; 1 EACH SALVAGE SIGN TYPE C; 2 EACH SALVAGE MAIL BOX SUPPORT; 953 LIN FT SAWING BIT PAVEMENT (FULL DEPTH); 195 LIN FT REMOVE SEWER PIPE (STORM); 65 LIN FT REMOVE CURB & GUTTER; 20 SQ YD REMOVE CONCRETE WALK; 36 SQ YD REMOVE BITUMINOUS DRIVEWAY PAVEMENT; 1226 SQ YD REMOVE BITUMINOUS PAVEMENT; 10 CU YD EXCAVATION - COMMON; 1 HOUR STREET SWEEPER (WITH PICKUP BROOM); 458 TON AGGREGATE BASE CLASS 5; 7 TON BITUMINOUS PATCHING MIXTURE DRIVEWAY; 125 LIN FT 15" RC PIPE SEWER DES 3006 CL V; 605 LIN FT 24" RC PIPE SEWER DES 3006 CL V; 2 EACH CONSTRUCT BULKHEAD; 6 EACH CONNECT TO EXISTING STORM SEWER; 24 SQ YD WATERMAIN INSULATION; 10 EACH CASTING ASSEMBLY; 2 EACH INSTALL CASTING; 5.5 LIN FT CONST DRAINAGE STRUCTURE DESIGN N; 34.7 LIN FT CONST DRAINAGE STRUCTURE DES 48-4020; 10.6 LIN FT CONST DRAINAGE STRUCTURE DES 60-4020; 208 SQ FT 6" CONCRETE WALK; 62 LIN FT CONCRETE CURB & GUTTER DESIGN B424; 21 LIN FT CONCRETE CURB & GUTTER DESIGN B612; 45 SQ FT TRUNCATED DOMES; 2 EACH INSTALL MAIL BOX SUPPORT; 1 LUMP SUM TRAFFIC CONTROL SUPERVISOR; 1 LUMP SUM TRAFFIC CONTROL; 20 UDAY PORTABLE CHANGEABLE MESSAGE SIGN; 1 EACH INSTALL SIGN TYPE C; 1 EACH INSTALL APS PED PUSH BUTTON STATION; 14 EACH STORM DRAIN INLET PROTECTION; 100 LIN FT SEDIMENT CONTROL LOG TYPE ROCK; 357 SQ YD SODDING TYPE LAWN, all in accordance with specifications and bid forms.

All project plans, specifications, instructions for bidders, the bid form and all other requirements are available at https://hennepin.procureware.com.
Project Owner:

Luke Ulstad
1600 Prairie Drive
Medina, MN   55340
(612) 595-0380
luke.ulstad@hennepin.us
Project Engineer:

Luke Ulstad
1600 Prairie Drive
Medina, MN   55340
(612) 595-0380
luke.ulstad@hennepin.us