Project Number:
ST-003
Contract Number:
ST-003
Other Project Numbers:
Project Description:
S. 1st St/Greeley St/Williams St Reconstruction
Construction Location:
S. 1st St (Greeley St to George St), Greeley St (College Dr to Saratoga St) and Williams St (Maple St to George St)
City or Township:
Marshall
Bid Opening:
02/04/2022 9:00 AM
Expected Award Date:
02/08/2022
Project Start Date:
04/18/2022
Construction Start Date:
04/18/2022
Construction End Date:
10/21/2022
Work Type:
Reconstruct
Project Type:
Road and Street
Highest Funding Level:
Local
DBE Project:
No
The City of Marshall, Minnesota will receive electronic bids only via BidVAULT until 9:00 a.m. (local time) on Friday, February 4, 2022, for the following project in MARSHALL, MINNESOTA:

PROJECT ST-003: This project consists of the following: Reconstruction and utility replacement on South 1st Street from George Street to Greeley Street, Greeley Street from West College Drive to East Saratoga Street, and Williams Street from George Street to West Maple Street. All utilities will be replaced, including watermain, sanitary sewer, and storm sewer on South 1st Street, Greeley Street and Williams Street. This project will include new water and sewer services to the right-of-way. Other items of work included in this project are pavement removal, aggregate base, bituminous surfacing, concrete surfacing, sidewalks, curb and gutter and other minor work.

Prospective bidders must register as a Plan Holder to download plans and specifications. All bids shall be made electronically via BidVAULT and shall be accompanied by a cash deposit, cashier's check, bid bond or certified check, payable to the order of the City for not less than 10% of the bid. Instructions on submitting a bid electronically via BidVAULT can be found at the following: https://rtvision.atlassian.net/wiki/spaces/ONE/pages/12091421/Contractor+Guides. The cost to submit a bid is $25 plus a 3rd party payment processing fee.

A copy of the full Advertisement for Bid, Plans, and Specifications for this project can be found through the City of Marshall’s eGram website at https://egram.ci.marshall.mn.us. For any questions regarding this project, please contact Jessie Dehn, Assistant City Engineer, at Jessie.Dehn@ci.marshall.mn.us or 507-537-6773.

Jason R. Anderson, P.E.
Public Works Director/City Engineer
Project Major Items:
NumberItemUnitsQuantity
2106.607COMMON EXCAVATIONCU YD4,722.00
2211.607AGGREGATE BASE (CV) CLASS 5CU YD4,332.00
2360.609TYPE SP 9.5 WEARING COURSE MIX (3;C)TON2,720.00
2502.503/090606" PERF PVC PIPE DRAINL F6,056.00
2503.603/210088" PVC PIPE SEWERL F1,556.00
2504.602/000061" WATER SERVICE (COMPLETE)EACH51.00
2504.603/020066" PVC WATERMAINL F2,182.00
2504.603/020088" PVC WATERMAINL F1,088.00
2521.518/000404" CONCRETE WALKS F13,464.00
2531.503/02315CONCRETE CURB & GUTTER DESIGN B618L F5,008.00
Project Owner:

Anderson, Jason
344 West Main Street
Marshall, MN   56258
507-537-6773
jason.anderson@ci.marshall.mn.us
Project Engineer:

Dehn, Jessie
344 West Main Street
Marshall, MN   56258
507-537-6773
jessie.dehn@ci.marshall.mn.us