- Project Number:
- 612104
- Contract Number:
- 612104
- Other Project Numbers:
- 612104
- Project Description:
- 2021 Bike Trail Maintenance
- Construction Location:
- Multiple Locations on Pope County Bike Trail
- City or Township:
- Bid Opening:
- 06/03/2021 10:00 AM
- Expected Award Date:
- 06/15/2021
- Project Start Date:
- 08/16/2021
- Construction Start Date:
- 08/16/2021
- Construction End Date:
- 10/01/2021
- Work Type:
- Bituminous
- Project Type:
- Road and Street
- Highest Funding Level:
- Local
- DBE Project:
- No
Sealed Bids will be received until June 3rd, 2021, 10:00 AM, by the Pope County Highway Department, on behalf of the County Board of Commissioners, for the construction of CP 061-021-003, Bike Trail Full Depth Reclamation and Bituminous Surfacing locations in Pope County.
Project Major Items:
Number | Item | Units | Quantity |
---|
2112.519/00010 | SUBGRADE PREPARATION | RDST | 86.60 |
2215.504/00010 | FULL DEPTH RECLAMATION | S Y | 12,275.00 |
2221.509/00010 | SHOULDER BASE AGGREGATE CLASS 1 | TON | 305.00 |
2360.509/12200 | TYPE SP 9.5 WEARING COURSE MIX (2;B) | TON | 1,880.00 |