- Project Number:
- Paver-Laid Patch (2021)
- Contract Number:
- 20212
- Other Project Numbers:
- Project Description:
- Paver-laid patching in Twin Lakes Park
- Construction Location:
- City or Township:
- Bid Opening:
- 05/25/2021 11:00 AM
- Expected Award Date:
- 06/14/2021
- Project Start Date:
- 06/14/2021
- Construction Start Date:
- 06/14/2021
- Construction End Date:
- 10/30/2021
- Work Type:
- Bituminous
- Project Type:
- Road and Street
- Highest Funding Level:
- Local
- DBE Project:
- No
NOTICE TO CONTRACTORS
Sealed Bids will be received until 11:00 a.m. on May 25, 2021 in the Auditor/Treasurers Office of the Lyon County Government Center, 607 West Main St., Marshall, MN by E.J. Moberg, Lyon County Auditor/Treasurer on behalf of the Board of Commissioners for the following projects.
SAP 042-609-036, SAP 042-616-005, CP 59-21, CP 74-21, PAVER-LAID PATCH
Bituminous Overlay
See the Lyon County website, www.lyonco.org, for complete Notice and bid information.
Electronic version of the plans and proposal are available to view/download at https://egram.lyonco.org/. Look under âProjects in Biddingâ.
Aaron VanMoer, P.E.
Lyon County Engineer
Project Major Items:
Number | Item | Units | Quantity |
---|
2360.501 | TYPE SP 12.5 WEARING COURSE MIXTURE PAVER LAID PATCHING | TON | 129.00 |