- Project Number:
- SP 109-020-014
- Contract Number:
- Other Project Numbers:
- 2105-21 027-752-036 STPF 2721 (085)
- Project Description:
- Reconstruction of Brooklyn Boulevard (CSAH 152) from Bass Lake Road (CSAH 10) to I-94 in Brooklyn Center.
- Construction Location:
- Brooklyn Boulevard (CSAH 152)
- City or Township:
- Brooklyn Center
- Bid Opening:
- 04/09/2021 10:00 AM
- Expected Award Date:
- 05/10/2021
- Project Start Date:
- 05/17/2021
- Construction Start Date:
- 05/17/2021
- Construction End Date:
- 09/30/2022
- Work Type:
- Reconstruct
- Project Type:
- Road and Street
- Highest Funding Level:
- Federal
- DBE Project:
- Yes
ADVERTISEMENT FOR BIDS: The City of Brooklyn Center, Minnesota, hereby gives notice that sealed Bids will be received in the office of the City Clerk, 6301 Shingle Creek Parkway, Brooklyn Center, Minnesota, for the following Project: Improvement Project NOS. 2021-05, SP NOS. 109-020-014, 027-752-036 and SAP No. 109-101-006, Brooklyn Boulevard (CSAH 152) Reconstruction.
Sealed Bids will be received until 10:00 a.m., local time, on Friday, April 9, 2021, at the Brooklyn Center City Offices, at which time and place the City Engineer, or their designated representatives, shall publicly open and read aloud the Bids. The project shall consist of the following approximate quantities:
Excavation: 25,000 C.Y.
Storm Sewer Pipe: 6,800 L.F.
DIP Water Main: 300 L.F.
Sanitary Sewer Pipe: 1,100 L.F.
Inplace Sewer Pipe Lining: 1,500 L.F.
Bituminous Pavement: 14,000 TONS
Bituminous Trail: 59,000 S.F.
Concrete Driveway Pavement: 1,400 S.Y.
Concrete Curb and Gutter: 18,000 L.F.
Concrete Sidewalk: 69,000 S.F.
Signal System: 2 EACH
Landscape Monument: 1 EACH
Lighting Unit: 78 EACH
Striping Multi Component Ground In: 7,000 L.F.
Sodding: 22,000 S.Y.