Project Number:
CP 020-622-001, etc.
Contract Number:
22022
Other Project Numbers:
CP 020-622-002
CP 020-624-001
C-22-13
Project Description:
Bituminous pavement reclamation, bituminous surfacing, realignment, culvert replacements, and aggregate shouldering
Construction Location:
City or Township:
Bid Opening:
03/09/2022 11:00 AM
Expected Award Date:
03/22/2022
Project Start Date:
05/31/2022
Construction Start Date:
05/31/2022
Construction End Date:
10/31/2022
Work Type:
Bridge
Project Type:
Bridges
Highest Funding Level:
Local
DBE Project:
No
NOTICE TO CONTRACTORS: Sealed proposals will be received until 11:00 A.M. on March 9, 2022, at the Dodge County Government Services Building in Mantorville, Minnesota, on behalf of the Dodge County Board of Commissioners for the following described highway projects:


C.P. 020-622-001: Bituminous Pavement Reclamation and Bituminous Surfacing on Dodge County Road 22, 2.6 miles east of West Concord, MN

The approximate major quantities:

Full Depth Reclamation – 56,190 S.Y.; Wearing Course Mixture (3,C) – 15,920 Tons; Shoulder Base Aggregate – 1,250 Tons


C.P. 020-622-002: Bituminous Pavement Reclamation and Bituminous Surfacing on Dodge County Road 22, 4 miles north of Mantorville, MN

The approximate major quantities:

Full Depth Reclamation – 58,900 S.Y.; Wearing Course Mixture (3,C) – 16,171 Tons; Shoulder Base Aggregate – 3,000 Tons

C.P. 020-624-001: Bituminous Pavement Reclamation, Realignment, Culvert Replacement, and Bituminous Surfacing on Dodge County Road 24, 6.5 miles north of Mantorville, MN

The approximate major quantities:

Excavation Common – 16,888 C.Y.; Full Depth Reclamation – 84,771 S.Y.; Wearing Course Mixture (3,C) – 26,744 Tons; RC Pipe Apron – 42 each; RC Pipe Culvert – 294 L.F.; PP Pipe Culvert – 464 L.F.

C-22-13: Bituminous Pavement Mill and Overlay on Olmsted County Road 13, south of Pine Island, MN

The approximate major quantities:

Mill Bituminous Surface (2”) – 25,601 S.Y.; Wearing Course Mixture (3,C) – 2,869 Tons


Plans, proposals and specifications may be obtained from the Dodge County Engineer's Office, 16 South Airport Drive, Dodge Center, Minnesota 55927.

Counter Price $40.00 (Sales tax included) No Return
Delivered Price $60.00 (Sales tax included) No Return


Each bid must be accompanied by a Bidder's Bond made payable to Dodge County in a sum equal to at least 5% of the bid amount.

Bids must be sealed and addressed to Dodge County Administration, 721 Main St. N., Mantorville, MN 55955, and plainly labeled "Bid for C.P. 020-622-001, etc.”

The right is reserved to reject any or all bids and to waive any defects therein.


Jim Elmquist
County Administrator
Dodge County, Minnesota
Project Major Items:
NumberItemUnitsQuantity
2106.507/00010EXCAVATION - COMMONC Y14,318.00
2215.504/00010FULL DEPTH RECLAMATIONS Y199,861.00
2221.509/00030SHOULDER BASE AGGREGATE CLASS 2TON6,545.00
2232.504/00060MILL BITUMINOUS SURFACE (2.0")S Y25,601.00
2360.509/33300TYPE SP 19.0 WEARING COURSE MIXTURE (3,C)TON34,903.00
Project Owner:

Kohlnhofer, Guy W
16 S. Airport Dr.
Dodge Center, MN   55927
507-635-6332
374-2552
dodge.highway@co.dodge.mn.us
Project Engineer:

Kohlnhofer, Guy W
16 S. Airport Dr.
Dodge Center, MN   55927
507-635-6332
374-2552
guy.kohlnhofer@co.dodge.mn.us