- Project Number:
- CP 073-186-019
- Contract Number:
- Other Project Numbers:
- Project Description:
- Construction Location:
- City or Township:
- Bid Opening:
- 02/18/2021 11:00 AM
- Expected Award Date:
- 02/23/2021
- Project Start Date:
- 05/10/2021
- Construction Start Date:
- 05/10/2021
- Construction End Date:
- 09/30/2021
- Work Type:
- Surfacing
- Project Type:
- Road and Street
- Highest Funding Level:
- Local
- DBE Project:
- No
Stearns County Highway Project
Close April 10, 2020
St. Cloud, Minnesota
Advertisement for Bids â STEARNS COUNTY HAS IMPLEMENTED ONLINE PROJECT BIDDING USING THE QUEST CONSTRUCTION DATA NETWORK. ONLY ELECTRONIC BIDS WILL BE ACCEPTED THROUGH WWW.QUESTCDN.COM.
Sealed proposals will ONLY be received and accepted via the online electronic bid service through www.questcdn.com, until 11:00 A.M. on Thursday, February 18, 2021 for the contract listed below. Electronic bids will be opened publicly at the Stearns County Highway (Public Works) Department Building located at 455 28th Avenue South, Waite Park, MN 56387.
PROJECT NO.: CP 073-186-019
LOCATION: County Road 186
TYPE OF WORK: Bituminous Mill, Concrete Overlay, and Approach Panels
The County reserves the right to reject any or all bids and to waive any informalities.
Dated at St. Cloud, Minnesota this 25th day of January 2021.
Publish: Stearns County Web Site January 25 â February 17, 2021.
_________________________________________
Randy R. Schreifels
County Auditor-Treasurer