- Project Number:
- 20-10
- Contract Number:
- 20-10
- Other Project Numbers:
- 20-10
- Project Description:
- 2020 Drainage Improvements
- Construction Location:
- 2660 Civic Center Dr
- City or Township:
- Roseville
- Bid Opening:
- 04/17/2020 4:00 PM
- Expected Award Date:
- 04/20/2020
- Project Start Date:
- 04/27/2020
- Construction Start Date:
- 07/14/2020
- Construction End Date:
- 10/02/2020
- Work Type:
- Grading
- Project Type:
- Drainage
- Highest Funding Level:
- Local
- DBE Project:
- No
Drainage and grading improvements
Project Major Items:
Number | Item | Units | Quantity |
---|
2105.501/00012 | COMMON EXCAVATION (EV) | C Y | 1,700.00 |
2105.604/000331 | GEOTEXTILE FABRIC TYPE III NON-WOVEN | SY | 450.00 |
2503.603/06059 | 6" PERFORATED HDPE PIPE SEWER | L F | 380.00 |