Project Number:
SAP 019-614-016
Contract Number:
32494
Other Project Numbers:
CP 14-33 SAP 019-614-016
Project Description:
2020 Overlay & Misc. Projects
Construction Location:
City or Township:
Bid Opening:
04/07/2020 9:00 AM
Expected Award Date:
04/21/2020
Project Start Date:
05/11/2020
Construction Start Date:
05/11/2020
Construction End Date:
10/30/2020
Work Type:
Mill and Overlay
Project Type:
Road and Street
Highest Funding Level:
State
DBE Project:
No
The 2020 Dakota County Overlays & Miscellaneous Projects contract (Contract No. 32494) includes the following projects:

CP 09-59 & 09-60: Mill & overlay, pedestrian curb ramp improvements, utility repairs, and intersection revisions on CSAH 9 (Dodd Boulevard) from Ideal Way to north of 194th Street in Lakeville
CP 14-33: Mill & overlay, pedestrian curb ramp improvements, utility repairs, and signal revision on CSAH 14 (Mendota Road/Southview Boulevard) from TH 62 to TH 52 in Inver Grove Heights, West St. Paul, and South St. Paul
CP 26-61: Mill & overlay, pedestrian curb ramp improvements, utility repairs, and signal revision on CSAH 26 (70th Street) from Cahill Avenue to CSAH 56 in Inver Grove Heights
CP 26-62: Mill & overlay on CSAH 26 (Lone Oak Road) from TH 13 to CSAH 31 in Eagan
CP 28-60: Mill & overlay on CSAH 28 (80th Street) from TH 3 to 1700 feet east of TH 3 in Inver Grove Heights
CP 28-61: Mill & overlay, pedestrian curb ramp improvements, utility repairs, and signal revisions on CSAH 28 (80th Street) from CSAH 73 to CSAH 56 in Inver Grove Heights
CP 31-104: Mill & overlay, pedestrian curb ramp improvements, utility repairs, and signal revision on CSAH 31 (Pilot Knob Road) from CSAH 33 to Dolores Lane in Apple Valley and Eagan
CP 32-108: Mill & overlay, pedestrian curb ramp & median nose improvements, utility repairs, and signal revision on CSAH 32 (Cliff Road) from I-35E to CSAH 43 in Eagan
CP 42-158: Access closure on CSAH 42 at Lebanon Cemetery in Apple Valley
CP 46-51: Mill & overlay, pedestrian curb ramps, utility repairs, and signal revisions on CSAH 46 (160th Street) from west of Ipava Avenue to CSAH 23 in Lakeville, Burnsville, and Apple Valley
CP 46-55: Mill & overlay, pedestrian curb ramps, utility repairs, and signal revision on CSAH 46 (162nd Street) from I-35 to west of Ipava Avenue in Lakeville
CP 60-25: Drainage improvements at CSAH 60 & Jasmine Way in Lakeville
CP 73-33: Mill & overlay and utility repairs on CSAH 73 (Babcock Trail) from I-494 to 1000 feet north of CSAH 14 in Inver Grove Heights and West St. Paul

The major items of work include approximately:
530,000 SQ. YD. OF MILL BITUMINOUS SURFACE
63,600 TONS of 2360 WEARING COURSE MIXTURE
10 SIGNAL REVISIONS
34,900 SQ. FT. of CONCRETE WALK
17,300 LIN. FT. of CONCRETE CURB & GUTTER
294,000 LIN. FT. of PAVEMENT MARKINGS- MULTI COMP
5,600 SQ. FT. of PAVEMENT MESSAGE/CROSSWALK-MULTI COMP
11,200 LIN. FT. of PAVEMENT MARKINGS- PREFORM TAPE
2,300 SQ. FT. of PAVEMENT MESSAGE/CROSSWALK-PREFORM TAPE
Project Owner:

Anton, Thomas J
Dakota County WSC
14955 Galaxie Ave
Apple Valley, MN   55124
(952) 891-7120
(952) 891-7127
tom.anton@co.dakota.mn.us
Project Engineer:

Goddard, Del
Dakota County Empire Maintenance Facility
2800 160th Street W
Rosemount, MN   55068
(952) 891-7922
(952) 891-7909
del.goddard@co.dakota.mn.us