- Project Number:
- 20-13
- Contract Number:
- Other Project Numbers:
- Project Description:
- 2020 Mill & Overlay Project
- Construction Location:
- Dillon St, Fifth St, Woodcrest Rd, Auger Ave, Dell Ct N, Dell Ct S, Dell St,
Elm St, Highland Ave, Midland Ct, Rooney Pl, Sunrise Ct, Willow Ct E, Willow Ct,
- City or Township:
- White Bear Lake
- Bid Opening:
- 03/25/2020 1:00 PM
- Expected Award Date:
- 04/14/2020
- Project Start Date:
- 04/15/2020
- Construction Start Date:
- 05/11/2020
- Construction End Date:
- 09/30/2020
- Work Type:
- Mill and Overlay
- Project Type:
- Road and Street
- Highest Funding Level:
- State
- DBE Project:
- No
Notice is hereby given that sealed bids will be received at the White Bear Lake City Hall, 4701 Highway 61, White Bear Lake, Minnesota 55110, until 1:00 p.m. on Wednesday, March 25, 2020 at which time they will be publicly opened and read aloud by the City Engineer and Engineering Secretary, said bids to be for the furnishing of all labor and materials to complete the following described local improvements under Minnesota Statutes, Chapter 429:
Mill and Overlay on: Dillon Street (Fifth Street to Seventh Street), Fifth Street (Karen Place to Wood Avenue), Woodcrest Road (Seventh Street to Ninth Street), Auger Avenue (Elm Street to County Road E), Dell Street (Willow Avenue to 140â™ west of Midland Avenue), Dell Court N (Dell Street to end cul-de-sac), Dell Court S (Dell Street to end cul-de-sac), Elm Street (Willow Avenue to White Bear Avenue), Highland Avenue (Elm Street to County Road E), Midland Court (Elm Street to end cul-de-sac), Rooney Place (Dell Street to end cul-de-sac), Sunrise Court (Highland Avenue to end cul-de-sac), Willow Court East (Willow Avenue to Willow Court), Willow Court (south limits to Elm Street), Jansen Avenue (Bellaire Avenue to Glen Oaks Avenue), Glen Oaks Avenue (Elm Drive to end cul-de-sac), Glen Oaks Court (Glen Oaks Avenue to end cul-de-sac), Rolling View Court (Rolling View Drive to end cul-de-sac), Rolling View Drive (Glen Oaks Avenue to County Road E), Oak Court (Bellaire Avenue to end cul-de-sac), and Orchard Circle (Orchard Lane to end cul-de-sac).
Project Major Items:
Number | Item | Units | Quantity |
---|
2104.504 | Remove Bituminous Pavement | S.Y. | 39,000.00 |
2105.507 | Common Excavation | C.Y. | 1,000.00 |
2105.619 | Minor Grading | Road Sta | 112.00 |
2211.509 | MnDOT CL 5 Aggregate Base (Recycled) | Ton | 1,100.00 |
2232.504 | Mill Bituminous Pavement | S.Y. | 23,000.00 |
2360.509 | Bituminous Wear Course | Ton | 9,000.00 |
2521.518 | 4" Concrete Walk | S.F. | 15,000.00 |
2531.503 | Concrete Curb & Gutter B618 | L.F | 2,000.00 |
2575.504 | Sodding Type Lawn | S.Y. | 4,000.00 |
2575.604 | Hydro Mulch | S.Y. | 1,000.00 |