- Project Number:
- SAP 149-117-009
- Contract Number:
- Other Project Numbers:
- 2019-A43 SAP 149-117-009
- Project Description:
- Roundabout Construction and Pedestrian Tunnel Installation
- Construction Location:
- Trunk Highway 246 and Jefferson Parkway
- City or Township:
- Northfield
- Bid Opening:
- 02/27/2020 2:00 PM
- Expected Award Date:
- 03/10/2020
- Project Start Date:
- 03/10/2020
- Construction Start Date:
- 05/04/2020
- Construction End Date:
- 11/06/2020
- Work Type:
- Reconstruct
- Project Type:
- Road and Street
- Highest Funding Level:
- State
- DBE Project:
- No
Roundabout Construction and Pedestrian Tunnel installation on TH 246 and Jefferson Parkway.
Project Major Items:
Number | Item | Units | Quantity |
---|
2105.507 | MUCK EXCAVATION | C Y | 3,648.00 |
2106.507 | COMMON EMBANKMENT (CV) | C Y | 20,210.00 |
2106.507 | EXCAVATION - COMMON | C Y | 18,455.00 |
2211.507 | AGGREGATE BASE (CV) CLASS 5 | C Y | 2,843.00 |
2360.509 | TYPE SP 12.5 NON WEAR COURSE MIX (3;C) | TON | 1,263.00 |
2360.509 | TYPE SP 9.5 WEARING COURSE MIX (3;B) | TON | 573.00 |
2360.509 | TYPE SP 9.5 WEARING COURSE MIX (3;C) | TON | 845.00 |
2412.503 | 16X10 PRECAST CONCRETE BOX CULVERT | L F | 324.00 |
2531.503 | CONCRETE CURB & GUTTER DESIGN B618 | L F | 6,195.00 |