- Project Number:
- CP 0000-278672R
- Contract Number:
- Other Project Numbers:
- CP 0000-278672R
- Project Description:
- CP 0000-278672R - South Crushing 2019
- Construction Location:
- City or Township:
- Bid Opening:
- 07/11/2019 10:00 AM
- Expected Award Date:
- 08/06/2019
- Project Start Date:
- 08/06/2019
- Construction Start Date:
- 08/06/2019
- Construction End Date:
- 10/18/2019
- Work Type:
- Aggregate
- Project Type:
- Road and Street
- Highest Funding Level:
- Local
- DBE Project:
- No
CP 0000-278672R (South Crushing 2019)
Crush, Screen and Stockpile Aggregate, Class 5 (Modified) and Screen and Stockpile Sand
Project Major Items:
Number | Item | Units | Quantity |
---|
2211.609 | CRUSH, SCREEN, & STOCKPILE AGG CL 5 (MOD) | TON | 19,500.00 |
2211.609 | CRUSH, SCREEN, & STOCKPILE AGG CL 5 (MOD) | TON | 21,800.00 |
2211.609 | CRUSH, SCREEN, & STOCKPILE AGG CL 5 (MOD) | TON | 23,000.00 |
2211.609 | CRUSH, SCREEN, & STOCKPILE AGG CL 5 (MOD) | TON | 26,000.00 |