- Project Number:
- SAP 009-599-029
- Contract Number:
- Other Project Numbers:
- 1901 SAP 009-599-029
- Project Description:
- SAP 009-599-029 on Overlie Road (T-122), approximately 3324 feet west of CSAH 5. Replace CMP culvert over Little Otter Creek with Bridge 09J48 and approaches.
- Construction Location:
- On T-122 (Overlie Road) approx. 3324' West of CSAH 5
- City or Township:
- Bid Opening:
- 05/28/2019 10:00 AM
- Expected Award Date:
- 05/28/2019
- Project Start Date:
- 07/01/2019
- Construction Start Date:
- 07/01/2019
- Construction End Date:
- 09/15/2019
- Work Type:
- Bridge
- Project Type:
- Bridges
- Highest Funding Level:
- State
- DBE Project:
- No
The Carlton County Transportation Department will receive bids for the following project(s): SAP 009-599-029, Approach Grading and Bridge No. 09J48. The bids must be submitted electronically to Bid Express® at https://www.bidexpress.com before MAY 28, 2019, 10:00 AM CST. The majority of the work on this project involves Remove Pipe Culverts, 14 x 5 Precast Concrete Box Culvert with End Sections, and Approaches. The Proposal and Specifications are available at the Bid Express® website. The Plans are available at the Departments eGram website at https://egram.co.carlton.mn.us. After an acceptable audit of the bids received, a recommendation for award to the lowest responsible bidder will be presented to the Carlton County Board of Commissioners at the County Board Meeting, 1630 County Road 61, Carlton MN, on MAY 28, 2019, 4:00 PM CST.
Project Major Items:
Number | Item | Units | Quantity |
---|
2104.503 | REMOVE PIPE CULVERTS | L F | 50.00 |
2105.601 | DEWATERING | LS | 1.00 |
2105.601 | TEMPORARY STREAM DIVERSION SYSTEM | LS | 1.00 |
2118.509 | AGGREGATE SURFACING CLASS 5 | TON | 371.00 |
2412.502 | 14X5 PRECAST CONCRETE BOX CULV END SECT | EACH | 2.00 |
2412.503 | 14X5 PRECAST CONCRETE BOX CULVERT | L F | 40.00 |
2451.507 | STRUCTURE EXCAVATION CLASS U | C Y | 675.00 |
2575.504 | RAPID STABILIZATION METHOD 4 | S Y | 132.00 |