- Project Number:
- COUNTY WIDE STRIPING
- Contract Number:
- Other Project Numbers:
- Project Description:
- COUNTY WIDE CENTERLINE AND EDGE LINE STRIPING
- Construction Location:
- City or Township:
- Bid Opening:
- 04/26/2019 10:00 AM
- Expected Award Date:
- 05/07/2019
- Project Start Date:
- 08/12/2019
- Construction Start Date:
- 08/12/2019
- Construction End Date:
- 08/31/2019
- Work Type:
- Traffic Marking/Striping
- Project Type:
- Road and Street
- Highest Funding Level:
- State
- DBE Project:
- No
NOTICE
NOTICE TO CONTRACTORS - Sealed bids will be received until 10:00a.m., Friday, April 26th, 2019, by Darrell Pettis, County Administrator of Le Sueur County, 88 South park Avenue, Le Center, Minnesota on behalf of the County Board of Commissioners for the centerline and edge line striping on 209.54 miles of county roadways.
The approximate major quantities are as follows:
4 inch Wide White Edge Stripe - 6837 gallons
4 inch Wide Yellow Centerline Skips and No Passing Zones - 3679 gallons
Specifications and special provisions may be obtained at the County Highway Engineer's Office, 88 South Park Avenue, Le Center, Minnesota 56057, telephone 507-357-8210.
A certified check or a corporate surety bond, made payable to the Treasurer of Le Sueur County, must accompany bids in an amount of not less than five percent (5%) of total bid.
The County Board reserves the right to reject any or all bids and to waive any defects therein.
Darrell Pettis
County Administrator
Le Sueur County, Minnesota
Please publish for three (3) consecutive weeks as a legal ad, starting with the week of your April 3rd, 2019 publication.
Billing Address:
Le Sueur County Highway Department
88 South Park Avenue
Le Center, MN 56057
Attn: Colleen Baker
507-357-8210
Please provide our office with an affidavit of publication.
Project Major Items:
Number | Item | Units | Quantity |
---|
| | | 0.00 |
2582.503 | 4" BROKEN & SOLID LINE YELLOW PAINT | GALLONS | 3,679.00 |
2582.503 | 4" SOLID LINE WHITE PAINT | GALLONS | 6,837.00 |