- Project Number:
- 19-01/19-06
- Contract Number:
- Other Project Numbers:
- Project Description:
- Street and Utility Reconstruction
- Construction Location:
- Fourth Street, Fifth Street, Sixth Street, Seventh Street, Johnson Avenue,
Morehead Avenue, Various Alleys and Garden Lane
- City or Township:
- White Bear Lake
- Bid Opening:
- 04/03/2019 11:00 AM
- Expected Award Date:
- 04/09/2019
- Project Start Date:
- 04/10/2019
- Construction Start Date:
- 04/22/2019
- Construction End Date:
- 10/11/2019
- Work Type:
- Reconstruct
- Project Type:
- Road and Street
- Highest Funding Level:
- Local
- DBE Project:
- No
Notice is hereby given that sealed bids will be received at the White Bear Lake City Hall, 4701 Highway 61, White Bear Lake, Minnesota 55110, until 11:00 a.m. on Wednesday, April 3, 2019 at which time they will be publicly opened and read aloud by the City Engineer and Engineering Secretary, said bids to be for the furnishing of all labor and materials to complete the following described local improvements under Minnesota Statutes, Chapter 429:
Street reconstruction on: Fourth Street (Stewart Avenue to Johnson Avenue), Fifth Street (Stewart Avenue to Lake Avenue N), Sixth Street (Stewart Avenue to Lake Avenue N), Seventh Street (Stewart Avenue to Lake Avenue N), Morehead Avenue (Lake Avenue N to Seventh Street), Johnson Avenue (Fourth Street to Seventh Street), and Various Alleys (Alleys 1-6), and Garden Lane (Lemire Lane to Bald Eagle Avenue)
Project Major Items:
Number | Item | Units | Quantity |
---|
2104.504 | Remove Bituminous Pavement | S.Y. | 24,000.00 |
2105.507 | Common Excavation | C.Y. | 11,000.00 |
2211.509 | MnDOT CL 5 Aggregate Base | Ton | 10,000.00 |
2360.509 | Bituminous Wearing Course | Ton | 5,000.00 |
2360.618 | Bituminous Driveway Pavement | S.F. | 20,000.00 |
2503.503 | Storm Sewer Pipe | L.F. | 3,200.00 |
2503.602 | Santiary Sewer Wye Repairs | Each | 10.00 |
2504.602 | Expose Water service or Watermain | Each | 70.00 |
2504.603 | 1" Type K Copper Pipe | L.F. | 2,000.00 |
2504.603 | 6" Watermain Ductile Iron CL 52 | L.F. | 800.00 |
2504.603 | 8" Watermain Ductile Iron CL 52 | L.F. | 400.00 |
2531.503 | Concrete Curb & Gutter | L.F. | 16,000.00 |
2531.618 | 6" Driveway Pavement | S.F. | 8,000.00 |
2574.507 | Loam Topsoil Borrow | C.Y. | 2,000.00 |
2575.504 | Sod Type Lawn | S.Y. | 20,000.00 |