- Project Number:
- SAP 066-676-002
- Contract Number:
- 1973
- Other Project Numbers:
- SAP 066-676-002
- Project Description:
- CSAH 76 Reconstruction
- Construction Location:
- CSAH 76 (Acorn Tr/Baseline Rd) from CSAH 9 to CSAH 8.
- City or Township:
- North of Faribault
- Bid Opening:
- 03/21/2019 10:00 AM
- Expected Award Date:
- 03/26/2019
- Project Start Date:
- 05/06/2019
- Construction Start Date:
- 05/06/2019
- Construction End Date:
- 07/25/2020
- Work Type:
- Reconstruct
- Project Type:
- Road and Street
- Highest Funding Level:
- State
- DBE Project:
- No
NOTICE TO CONTRACTORS
ADVERTISEMENT FOR BIDS
SAP 066-676-002 âÂÂ" CSAH 76 Reconstruction
Sealed proposals will be received until 10:00 A.M., Thursday, March 21, 2019 by the Rice County Board of Commissioners at the office of the County Engineer, Rice County Highway Building, 610 NW 20th Street, Faribault, Minnesota, 55021, for the letting of a contract for the following project: CSAH 76 Reconstruction.
Project Major Items:
Number | Item | Units | Quantity |
---|
| 18” CS Pipe Culvert | Lin Ft | 1,119.00 |
| 18” RC Pipe Sewer DES 3006 CL III | Lin Ft | 1,247.00 |
| 4” Dble Solid Line Multi Comp | Lin Ft | 4,300.00 |
| 4” Perf PE Pipe Drain | Lin Ft | 21,385.00 |
| 4” Solid Line Multi Comp Gr In (WR) | Lin Ft | 3,404.00 |
| 6” Solid Line Multi Comp Gr In (WR) | Lin Ft | 21,490.00 |
| Aggregate Base Class 2 | Ton | 100.00 |
| Aggregate Base Class 5Q | Ton | 16,165.00 |
| Common Embankment (CV) (P) | Cu Yd | 32,200.00 |
| Concrete Curb & Gutter Design B424 | Lin Ft | 1,513.00 |
| Erosion Control Blankets Category 3N | Sq Yd | 24,500.00 |
| Excavation - Common (P) | Cu Yd | 46,179.00 |
| Full Depth Reclamation (P) | Sq Yd | 31,585.00 |
| Mill Bituminous Surface (1.5”) (P) | Sq Yd | 26,760.00 |
| Seeding | Acre | 48.00 |
| Select Granular Borrow | Ton | 31,295.00 |
| Subgrade Soil Modification | Sq Yd | 57,900.00 |
| Type SP 12.5 Non Wear Course Mix (3,C) | Ton | 5,970.00 |
| Type SP 12.5 Wearing Course Mix (3,C) | Ton | 6,085.00 |
| Type SP 9.5 Wearing Course Mix (3,C) | Ton | 4,620.00 |