- Project Number:
- 2019 Resurfacing
- Contract Number:
- Other Project Numbers:
- Project Description:
- 2019 Resurfacing Projects
- Construction Location:
- City or Township:
- Bid Opening:
- 02/21/2019 11:00 AM
- Expected Award Date:
- 03/12/2019
- Project Start Date:
- 05/13/2019
- Construction Start Date:
- 05/13/2019
- Construction End Date:
- 09/30/2019
- Work Type:
- Bituminous
- Project Type:
- Road and Street
- Highest Funding Level:
- Local
- DBE Project:
- No
Advertisement for Bids - Sealed proposals will be received at the Office of the County Auditor, Stearns County Administration Center, Room 148, 705 Courthouse Square, St. Cloud, Minnesota 56303, until 11:00 A.M. on Thursday February 21, 2019 for the contract listed below:
PROJECT NOS.: 2019 Bit Patch, SAP 073-617-039, SAP 073-618-015, SAP 073-625-002, SAP 073-630-017, SAP 073-632-019, SAP 073-633-006, SAP 073-643-006, SAP 073-648-003, SAP 073-652-003, CP 147-019-020, CP 150-019-012, CP 150-019-020, CP 151-019-013, CP 192-019-027, 385th Street, 295th Street, Birch Park Trail(Millwood Twp.), 155th Street, Caldron Rd., Caisson Rd.(Maine Prairie Twp.).
Dated at St. Cloud, Minnesota this 28th day of January 2019.
Publish: Stearns County Website January 28 February 20, 2019
_________________________________________
Randy R. Schreifels
County Auditor-Treasurer