Number | Item | Units | Quantity |
---|
2021.501 | MOBILIZATION | LUMP SUM | 1.00 |
2021.501 | MOBILIZATION | LUMP SUM | 1.00 |
2021.501 | MOBILIZATION | LUMP SUM | 1.00 |
2021.501 | MOBILIZATION | LUMP SUM | 1.00 |
2021.501 | MOBILIZATION | LUMP SUM | 1.00 |
2021.501 | MOBILIZATION | LUMP SUM | 1.00 |
2021.501 | MOBILIZATION | LUMP SUM | 1.00 |
2021.501 | MOBILIZATION | LUMP SUM | 1.00 |
2021.501 | MOBILIZATION | LUMP SUM | 1.00 |
2021.501 | MOBILIZATION | LUMP SUM | 1.00 |
2021.601 | RAILROAD PROTECTIVE SERVICES | LUMP SUM | 1.00 |
2021.601 | RAILROAD PROTECTIVE SERVICES | LUMP SUM | 1.00 |
2021.601 | RAILROAD PROTECTIVE SERVICES | LUMP SUM | 1.00 |
2021.601 | RAILROAD PROTECTIVE SERVICES | LUMP SUM | 1.00 |
2021.601 | RAILROAD PROTECTIVE SERVICES | LUMP SUM | 1.00 |
2021.601 | RAILROAD PROTECTIVE SERVICES | LUMP SUM | 1.00 |
2021.601 | RAILROAD PROTECTIVE SERVICES | LUMP SUM | 1.00 |
2021.601 | RAILROAD PROTECTIVE SERVICES | LUMP SUM | 1.00 |
2021.601 | RAILROAD PROTECTIVE SERVICES | LUMP SUM | 1.00 |
2021.601 | RAILROAD PROTECTIVE SERVICES | LUMP SUM | 1.00 |
2118.509 | AGGREGATE SURFACING CLASS 5 | TON | 12.00 |
2118.509 | AGGREGATE SURFACING CLASS 5 | TON | 12.00 |
2118.509 | AGGREGATE SURFACING CLASS 5 | TON | 12.00 |
2118.509 | AGGREGATE SURFACING CLASS 5 | TON | 12.00 |
2118.509 | AGGREGATE SURFACING CLASS 5 | TON | 12.00 |
2118.509 | AGGREGATE SURFACING CLASS 5 | TON | 12.00 |
2118.509 | AGGREGATE SURFACING CLASS 5 | TON | 12.00 |
2118.509 | AGGREGATE SURFACING CLASS 5 | TON | 20.00 |
2118.509 | AGGREGATE SURFACING CLASS 5 | TON | 20.00 |
2118.509 | AGGREGATE SURFACING CLASS 5 | TON | 24.00 |
2123.610 | SKID LOADER | HOUR | 5.00 |
2123.610 | SKID LOADER | HOUR | 5.00 |
2123.610 | SKID LOADER | HOUR | 5.00 |
2123.610 | SKID LOADER | HOUR | 5.00 |
2123.610 | SKID LOADER | HOUR | 5.00 |
2123.610 | SKID LOADER | HOUR | 5.00 |
2123.610 | SKID LOADER | HOUR | 5.00 |
2123.610 | SKID LOADER | HOUR | 5.00 |
2123.610 | SKID LOADER | HOUR | 5.00 |
2123.610 | SKID LOADER | HOUR | 10.00 |
2123.610 | STEEL-WHEELED ROLLER | HOUR | 5.00 |
2123.610 | STEEL-WHEELED ROLLER | HOUR | 5.00 |
2123.610 | STEEL-WHEELED ROLLER | HOUR | 5.00 |
2123.610 | STEEL-WHEELED ROLLER | HOUR | 5.00 |
2123.610 | STEEL-WHEELED ROLLER | HOUR | 5.00 |
2123.610 | STEEL-WHEELED ROLLER | HOUR | 5.00 |
2123.610 | STEEL-WHEELED ROLLER | HOUR | 5.00 |
2123.610 | STEEL-WHEELED ROLLER | HOUR | 5.00 |
2123.610 | STEEL-WHEELED ROLLER | HOUR | 5.00 |
2123.610 | STEEL-WHEELED ROLLER | HOUR | 10.00 |
2123.610 | TRACTOR MOUNTED BACKHOE-LOADER | HOUR | 3.00 |
2360.509 | TYPE SP 12.5 WEARING COURSE MIX (3;B) | TON | 54.00 |
2360.509 | TYPE SP 12.5 WEARING COURSE MIX (3;B) | TON | 64.00 |
2360.509 | TYPE SP 12.5 WEARING COURSE MIX (3;B) | TON | 64.00 |
2360.509 | TYPE SP 12.5 WEARING COURSE MIX (3;B) | TON | 80.00 |
2360.509 | TYPE SP 12.5 WEARING COURSE MIX (3;B) | TON | 84.00 |
2360.509 | TYPE SP 12.5 WEARING COURSE MIX (3;B) | TON | 84.00 |
2360.509 | TYPE SP 12.5 WEARING COURSE MIX (3;B) | TON | 87.00 |
2360.509 | TYPE SP 12.5 WEARING COURSE MIX (3;B) | TON | 94.00 |
2360.509 | TYPE SP 12.5 WEARING COURSE MIX (3;B) | TON | 102.00 |
2360.509 | TYPE SP 12.5 WEARING COURSE MIX (3;B) | TON | 108.00 |
2563.601 | TRAFFIC CONTROL | LUMP SUM | 1.00 |
2563.601 | TRAFFIC CONTROL | LUMP SUM | 1.00 |
2563.601 | TRAFFIC CONTROL | LUMP SUM | 1.00 |
2563.601 | TRAFFIC CONTROL | LUMP SUM | 1.00 |
2563.601 | TRAFFIC CONTROL | LUMP SUM | 1.00 |
2563.601 | TRAFFIC CONTROL | LUMP SUM | 1.00 |
2563.601 | TRAFFIC CONTROL | LUMP SUM | 1.00 |
2563.601 | TRAFFIC CONTROL | LUMP SUM | 1.00 |
2563.601 | TRAFFIC CONTROL | LUMP SUM | 1.00 |
2563.601 | TRAFFIC CONTROL | LUMP SUM | 1.00 |