- Project Number:
- CP 71-PM-018
- Contract Number:
- 17008
- Other Project Numbers:
- CP 71-PM-018
- Project Description:
- 2018 Pavement Markings
- Construction Location:
- City or Township:
- Bid Opening:
- 06/05/2018 1:15 PM
- Expected Award Date:
- 06/26/2018
- Project Start Date:
- 07/09/2018
- Construction Start Date:
- 07/09/2018
- Construction End Date:
- 10/26/2018
- Work Type:
- Surfacing
- Project Type:
- Road and Street
- Highest Funding Level:
- Local
- DBE Project:
- No
ADVERTISEMENT FOR BIDS
2018 PAVEMENT MARKINGS
CP 71-PM-018
SHERBURNE COUNTY, MINNESOTA
Notice is hereby given that sealed Bid Proposal Packages will be received by the Sherburne County Engineer at the office of the undersigned until 1:15 PM on the 5th day of June, 2018.
The Major Quantities of Work are:
7,500 Gallon Yellow Striping Paint
6,100 Gallon White Striping Paint
108,800 Pounds Glass Beads
Receipt of Bid Proposal: Bids will be received at the Public Works Department, located at the Sherburne County Government Center, 13880 Business Center Drive, Elk River MN 55330 until 1:15 PM, June 5, 2018.
Bid Opening: Proposals will be opened publicly by the County Engineer after the hour set for receiving bids at the Sherburne County Government Center, Spruce Room; 13880 Business Center Drive, Elk River MN 55330.
Plans and specifications may be examined at the office of the Sherburne County Highway Engineer, 425 Jackson Avenue, Elk River, Minnesota 55330, or at http://www.co.sherburne.mn.us/publicworks/index.php and follow the Construction Projects & Bids (eGram) link. A user ID and password is required to download the Plans and Specifications. Contact Public Works at 763-765-3300 to obtain.
The cost to download the Plans & Specifications is free.
The cost to obtain a hard copy of the Plans & Specifications is $50.00 with an additional $10.00 mailing fee.
TO SUBMIT A BID ? A Bid Proposal Package must be purchased. The cost to obtain the Bid Proposal Package is $10.00. Requests are made to the Sherburne County Engineer, 425 Jackson Ave., Elk River, MN 55330-4601.
Requests must be accompanied by check, draft, or money order, payable to the Sherburne County Treasurer. Bids must be accompanied by a Certified Check or Bidder?s Bond made payable to the Sherburne County Treasurer as a proposal guarantee for at least 5% of the amount of the bid.
No bidder may withdraw their bid (which shall include the Certified Check or the Bidder?s Bond) within 15 days after the scheduled closing time for the receipt of bids.
The County Board will consider award of the contract at the June 26, 2018 County Board Meeting contingent upon County Engineer & County Attorney review. It is the County?s intent to begin construction July 9, 2018 and be completed by October 26, 2018.