- Project Number:
- SP 064-070-005 / SAP 064-611-012
- Contract Number:
- 18-5
- Other Project Numbers:
- SAP 064-611-012 SP 064-070-005
- Project Description:
- Bit Resurf, Bit Shoulders, Ground-In Edge Line, Rumble Strips, Seal Coat & Guardrail on CSAH 11 between the Jct. CSAH 2 & the N County Line at the MN River; Sec 34, T-112-N R-34-W to Sec 12, T-112-N R-34-W; Sherman Twp, Redwood County, MN.
- Construction Location:
- CSAH 11 between the Jct. CSAH 2 and the North County Line at the Minnesota River
- City or Township:
- Sherman
- Bid Opening:
- 06/14/2018 10:30 AM
- Expected Award Date:
- 06/19/2018
- Project Start Date:
- 07/05/2018
- Construction Start Date:
- 07/15/2018
- Construction End Date:
- 09/30/2018
- Work Type:
- Bituminous
- Project Type:
- Road and Street
- Highest Funding Level:
- Federal
- DBE Project:
- Yes
SP 064-070-005/SAP 064-611-012; Bituminous Resurfacing, Bituminous Shoulders, Ground-In Edge Line, Rumble Strips, Seal Coat and Guardrail located on CSAH 11 between the Jct. CSAH 2 and the North County Line at the Minnesota River; Section 34, T-112-N R-34-W to Section 12, T-112-N R-34-W; Sherman Township, Redwood County, MN.
Project Major Items:
Number | Item | Units | Quantity |
---|
2104.503 | Remove Cable Guardrail | LF | 3,240.00 |
2221.509 | Shoulder Base Aggregate Cl-1 | TON | 1,925.00 |
2232.504 | Mill Bituminous Surface (1.5") | SY | 111,907.00 |
2232.603 | Milled Rumble Strips | LF | 65,900.00 |
2355.506 | Bituminous Material for Fog Seal | GAL | 10,528.00 |
2356.506 | Bituminous Material for Seal Coat | GAL | 26,319.00 |
2356.609 | Seal Coat Aggregate (FA-2) | TON | 1,053.00 |
2360.509 | Type SP 12.5 Wearing Course Mix (2,B) | TON | 19,170.00 |
2554.502 | End Treatment - Tangent Terminal | EACH | 8.00 |
2554.503 | Traffic Barrier Design B8338 | LF | 2,588.00 |
2563.602 | Raised Pavement Marker Temporary | EACH | 329.00 |
2582.503 | 4" Broken Line Paint (Yellow) | LF | 27,799.00 |
2582.503 | 4" Solid Line Paint (Yellow) | LF | 28,297.00 |
2582.503 | 6" Solid Line Multi Component Ground In (WR) | LF | 65,900.00 |